Skip to main content
AFARS

AFARS

Change Number: 2025-0711
Effective Date: 07/11/2025

<?xml encoding="UTF-8" ?>Subpart 5143.2 - Change Orders

Subpart 5143.2 - Change Orders

5143.204 Administration.

5143.204-70-6 Allowable profit.

The HCA shall ensure the profit allowed reflects the conventions under DFARS 243.204-70-6. See Appendix GG for further delegation.

5143.205 Contract clauses.

(c) The Contracting officer may change the period in which the contractor may assert claims under the clause at FAR 52.243-3, Changes—Time-and-Materials or Labor-Hours, to a period less than “30 days.”