The official AFARS regulation resides on the Army’s Knowledge Management Portal PAM. If you do not have CAC access to PAM, please visit the Army Contracting Enterprise’s public facing website “Army Connect” at https://www.army.mil/armycontracting#org-afars. The AFARS will return to Acquisition.gov upon completion of the RFO.

(Revised 01 October 2024)

Subpart 5143.2 - Change Orders

5143.204 Administration.

5143.204-70-5 Exceptions.

5143.204-70-6 Allowable profit.

5143.205 Contract clauses.

Subpart 5143.2 - Change Orders

5143.204 Administration.

5143.204-70-6 Allowable profit.

The HCA shall ensure the profit allowed reflects the conventions under DFARS 243.204-70-6. See Appendix GG for further delegation.

5143.205 Contract clauses.

(c) The Contracting officer may change the period in which the contractor may assert claims under the clause at FAR 52.243-3, Changes—Time-and-Materials or Labor-Hours, to a period less than “30 days.”