Subpart 5136.3 - Two-Phase Design-Build Selection Procedures

Subpart 5136.3 - Two-Phase Design-Build Selection Procedures

5136.301 Use of two-phase design-build selection procedures.

(b)(3)(vi) The head of the contracting activity, on a non-delegable basis, shall establish other criteria as described at FAR 36.301(b)(3)(vi).