E-2.1 Conduct Acquisition Planning

E-2.1 Conduct Acquisition Planning

The Program Managers and MATDEVs are required to document an IP strategy for all program types covered by DoDI 5010.44, Intellectual Property Acquisition and Licensing, starting at the Materiel Development Decision (MDD) and out through the declaration of a Program of Record (POR). The IP strategy is summarized in the Acquisition Strategy/Plan or SAMP and identifies the program’s comprehensive approach to managing the IP, data deliverables, and license rights requirements that will affect the program’s cost, schedule, and performance throughout the acquisition lifecycle. The IP strategy evolves over time and should continuously reflect the current status and desired goals of the program which is achieving greater competition and more affordable sustainment costs within the business objectives of the program. Acquisition planning includes all members of the IPT, to include PM, Engineering, Scientists, PCOs, Legal Counsel, etc.

Defense Acquisition University courses and learning modules to assist in Intellectual Property acquisitions are listed below. The courses are current as of the publication date of this appendix, please reference https://www.dau.edu/blogs/dau-intellectual-property-ip-and-data-rights-resources for additional offerings.

Courses/Learning Assets

CLM 002, Intellectual Property (IP) Valuation

CLE 068, Intellectual Property and Data Rights

CLE 069, Technology Transfer

CLE 019, Modular Open Systems Approach

CLM 071, Introduction to Data Management

CLM 072, Data Management Strategy Development

CLM 073, Data Management Planning System

CLM 075, Data Acquisition

CLM 076, Data Markings

CLM 077, Data Management Protection and Storage

LOG 2150, Technical Data Management

CACQ 008, Foundational IP Credential.

CACQ 011: Foundational Software Acquisition Management Credential

CON 0180: Data Rights

IP Strategy

When developing the comprehensive IP strategy and the capability requirements for performance and sustainment, consider the following in respect to IP, data deliverables, and associated license rights (for additional information consult Army Directive 2018-26, Enabling Modernization Through the Management of Intellectual Property.):

1. Develop an IP strategy that accounts for both short-term and long-term needs, covering the full lifecycle of the system or service. The IP strategy should continuously be assessed (e.g., sustainment reviews (SR)) and updated to reflect current status (i.e. evolving technology, reduced program cost or schedule, etc.) and desired goals/objectives. At a minimum, customize IP strategies based on the common, shared, and unique characteristics of the system and its components: system architecture and interfaces: product support/sustainment strategy: organic industrial base strategy of the DoD Component concerned; whether the item can be found in the commercial market: and whether the standard commercial licensing terms meet DoD needs. (NOTE: These can be considered strengths during a tradeoff, but cannot be mandated.)

2. Determine the appropriate sustainment approach to use for the IP strategy. The strategy should focus on achieving greater competition and more affordable sustainment costs. Anticipate the impact of sustainment costs within program business objectives over the entire system or service lifecycle. (NOTE: This can be considered a strength during a tradeoff, but cannot be mandated.)

3. Determine what kind of data (e.g., form, fit, and function data), software, and associated license rights are required/desired for all stages of the acquisition life cycle, including operation, maintenance, installation, and training (OMIT); modernization; and sustainment. The IP strategy should be customized to meet specific sustainment needs of the program (i.e., data deliverable and any required computer software source code).

4. The Government should consider the following techniques for securing data/software and associated/corresponding license rights:

a. Consider including contract provisions providing for the transfer of a detailed data/software package with the corresponding license rights to the Government if the original contractor goes out of business or drops the particular item from production.

b. Consider including data escrow provisions (see DFARS PGI 227.7203-2(b)(2)(ii)(D)).

5. Describe the Modular Open System Approach (MOSA) objectives that drive modularity decisions to support the operational and lifecycle needs. Describe how IP, and related matters, necessary to support the program’s use of modular open systems approaches, in accordance with 10 U.S.C. Sections §§ 3771-3775 and §§4401 - 4403, will be addressed. This includes providing guidance for how solicitations and contracts will:

a. Identify and require all major systems interfaces to be based on widely supported and consensus-based standards (if available and suitable), which are preferably non-proprietary.

b. Include requirements to acquire the appropriate IP rights in such major systems interfaces.

c. Include appropriate requirements for other non-major systems interfaces (e.g., interfaces necessary for segregation and reintegration activities).

d. Include request for Government Purpose Rights, when appropriate, for Circuit Card Assemblies in support of organic industrial base (OIB) DSOR and DSOS capabilities.

6. Appropriately reflect the IP strategy in both the solicitation and the resultant contract. Contents of both documents should include the IP, data deliverables, and associated license rights necessary to accomplish program objectives.

7. Request that offerors propose their own sustainment transition plan (to transition sustainment from their organization to the Government or another contractor) as an evaluation factor (technical sub factor – Supportability and Maintenance).

8. The Government should only seek the IP, data deliverables, and associated license rights necessary to support the mission of the program. In some instances, where offerors are willing to provide the Government with additional license rights to technical data and software, such additional costs may not be cost effective. Having an evaluation factor in a competitive procurement environment may drive down the associated costs for broader technical data or software license rights.

9. Consult with a Government IP attorney on IP, data deliverables, and associated license rights. Statutes and regulations related to technical data, software, and associated rights are set forth in 10 USC § Chapter 275 (and DFARS 227.7102-1, DFARS 227.7103-1, DFARS 227.7202-1, and DFARS 227.7203-1). The statute and DFARS regulations should be read carefully before procuring any technical data or software. Ensure the Government receives sufficient rights in technical data and software to enable organic or competitively established sustainment of items.

IP Strategy Checklist

*Adapted from: “Intellectual Property Acquisition and Licensing Checklist” DoD Brochure on Intellectual Property Strategy, Prepared by the Department of Defense Open Systems Architecture—Data Rights Team August 2014

Market Research

Once the Government’s requirements are sufficiently defined, market research in accordance with FAR Part 10, begins and is a coordinated effort by the PM or MATDEVs and the PCO. The market research technique utilized is at the discretion of the acquisition professionals. When conducting market research, consider the critical characteristics and needs of the requirement to include the following with respect to IP, data deliverables, and associated licensing rights:

1. Are there any hardware or software solutions that meet the requirement(s) that were developed using Government funding? If so, what?

2. Does Industry have any input to assist the Government in reaching the Government’s objectives or meeting the Government’s requirement(s)? If so, what?

3. Industry Standards

a. What are the usual terms in commercial transactions for the sale of the product or service you require?

b. Are the license and other intellectual property rights adequate for Government’s needs?

c. Are there any proprietary processes or materials (e.g., trade secrets) that may limit future competition?

d. Do the commercial terms and conditions violate laws or policies applicable to Government contracting?

 Note: Rights related to commercial software are governed by the standard commercial software license agreement, rather than any DFARS clauses.

e. Does the Government need/want to negotiate revisions to the standard commercial software license agreement in instances where the commercial software license agreement conflicts with Federal procurement law or does not meet the Government user’s needs?

 Note: In some instances, substantial revisions to the standard commercial software license agreement (e.g., additional software copies) may result in additional costs.

4. Technical Data Delivery Format

a. Contractors often do not have technical data in formats that DoD typically expects to receive. The Government should be willing to accept standard commercial data formats, to the maximum extent practicable.

b. Competitive: What are industry standards for technical data deliverable format(s)?

c. Sole Source: What is the contractor’s usual deliverable format for technical data?

5. Technology Maturity

a. How much of the software and/or hardware is mature?

b. How much of the software and/or hardware is still in development or testing?

c. What is the overall Technology Readiness Level (TRL)?

d. Software is typically not delivered 100 percent “bug” free. It may take several years to mature. The logistics product support/sustainment strategy should address software maintenance including “bug” fixes.

6. Support and Sustainment

a. Offerors typically provide software bug fix support, but length of support varies. The Government may consider bug fix support (including cost, length, and scope of such support) during source selection as a trade-off.

 Are software bug fixes supported?

 If so, how long are they supported?

b. Offerors may provide software upgrades and cybersecurity updates. The Government may consider offeror provided software upgrades (including cost, length, and scope of such support)

 Are software upgrades and cybersecurity updates provided at no additional cost?

 If so, how long are they provided? What are the terms and conditions?

c. Is there a plan to later modify deliverable hardware, data, or software?

d. Will a data package be required?

e. Will access to support and support-related technical information be obtained, for hardware and software, to cost-effectively maintain the system at each of the designated levels of maintenance and to foster competition for sources of support throughout the life-cycle.

f. Will government purpose rights (GPR) to a Level 3 Technical Data Package enable 3D Modeling for hardware to avoid vendor lock and allow for hardware repairs within the organic industrial base (OIB)?

7. Logistics

a. What is the approximate period of time required to prepare validated procedures addressing software and configuration file loading and to maintain the software baseline?

b. What period of time is required to transition and set-up the necessary tools and test equipment for the Government to conduct maintenance on the software baseline?

c. What is the approximate period of time required to train Government personnel on required hardware testing, troubleshooting, and repair procedures and procedures for maintaining the software baseline?