Subpart 2406.3 - Other Than Full and Open Competition
2406.302-2 Unusual and compelling urgency.
(d)(1)(ii) The HCA is the agency head's designee for the purposes of FAR 6.302-2(d)(1)(ii).
2406.303 Justifications.
Justifications for Other Than Full and Open Competition must be prepared and approved using the latest version of HUD Form 24012.
2406.304 Approval of the justification.
(a)(3) HUD's Chief Procurement Officer, as the Head of Contracting Activity, has delegated the authority to the Deputy Chief Procurement Officer to approve, in writing, justifications for other than full and open competition procurements for proposed contracts over $13.5 million, but not exceeding $68 million.
(c) A class justification for other than full and open competition shall be approved in writing by the Senior Procurement Executive.