2014.407 Mistakes in bids.

2014.407-3 Other mistakes disclosed before award.

The Director, Division of Contracts and Property Management, is delegated the authority to make the determinations concerning mistakes in bids, including those with obvious clerical errors, discovered prior to award. These determinations will be concurred in by legal counsel prior to notification of the bidder.

2014.407-4 Mistakes after award.

The cognizant contracting officer is delegated the authority to make determinations concerning mistakes disclosed after award in accordance with FAR 14.407-4. These determinations will be concurred in by legal counsel prior to notification of the contractor.