Skip to main content
GSAM

GSAM

Change Number: Change 178 GSAR Case 2020-G511
Effective Date: 03/25/2024

532.103 Progress payments under construction contracts.

532.103 Progress payments under construction contracts.

GSA Form 184 and, to the extent necessary, GSA Forms 184A and 184B, shall be prepared by Government personnel or agents of GSA to document satisfactory progress of work prior to processing each progress payment request submitted by the construction contractor in accordance with FAR 52.232-5 and 552.232-5. Generally, construction contractors are not considered agents of GSA. Certain other contractors, including, but not necessarily limited to, construction management contractors (CMs), however, may be considered agents of GSA if they are authorized to act on behalf of GSA to obtain the information for the referenced forms.