50.103-3 Contract adjustment.

50.103-3 Contract adjustment.

(a) Contractor requests. A contractor seeking a contract adjustment shall submit a request in duplicate to the contracting officer or an authorized representative. The request, normally a letter, shall state as a minimum-

(1) The precise adjustment requested;

(2) The essential facts, summarized chronologically in narrative form;

(3) The contractor’s conclusions based on these facts, showing, in terms of the considerations set forth in 50.103-1 and 50.103-2, when the contractor considers itself entitled to the adjustment; and

(4) Whether or not-

(i) All obligations under the contracts involved have been discharged;

(ii) Final payment under the contracts involved has been made;

(iii) Any proceeds from the request will be subject to assignment or other transfer, and to whom; and

(iv) The contractor has sought the same, or a similar or related, adjustment from the Government Accountability Office or any other part of the Government, or anticipates doing so.

(b) Contractor certification. A contractor seeking a contract adjustment that exceeds the simplified acquisition threshold shall, at the time the request is submitted, submit a certification by a person authorized to certify the request on behalf of the contractor that-

(1) The request is made in good faith; and

(2) The supporting data are accurate and complete to the best of that person’s knowledge and belief.