PGI 241.202 Procedures.

PGI 241.202 Procedures.

(2)(A) Do not use the connection charge provisions for the installation of Government-owned distribution lines and facilities. The acquisition of such facilities must be authorized by legislation and accomplished in accordance with FAR Part 36. Also, do not use the connection charge provisions for the installation of new facilities related to the supplier's production and general “backbone” system unless authorized by legislation.

(B) Construction labor standards ordinarily do not apply to construction accomplished under the connection charge provisions of this part. However, if installation includes construction of a public building or public work as defined in FAR 36.102, construction labor standards may apply.