Skip to main content
DFARS

DFARS

Change Number: DFARS Change 11/15/2024
Effective Date: 11/15/2024

Subpart 225.2 - BUY AMERICAN—CONSTRUCTIONMATERIALS

Subpart 225.2 - BUY AMERICAN—CONSTRUCTIONMATERIALS

225.202 Exceptions.

(a)(2) A nonavailability determination is not required for construction materials listed in FAR 25.104(a). For other materials, a nonavailability determination shall be approved at the levels specified in 225.103 Exceptions.(b)(ii). Use the estimated value of the construction materials to determine the approval level. A nonavailability determination is not required before January 1, 2030, if there is an offer for foreign construction material that exceeds 55 percent domestic content (also see FAR 25.204(b)(1)(ii) and (b)(2)(ii)).

225.206 Noncompliance.

(c)(4) Prepare any report of noncompliance in accordance with the procedures at 209.406-3 or 209.407-3 .

225.270 Energy savings service contracts.

If construction and construction materials will be used during the performance of a contract for DoD energy savings service requirements, see PGI 225.270 Energy savings service contracts. for additional guidance.

DFARS Parts

DFARS Appendix