915.404-4-70-7 Alternative techniques.
(a) Profit or fees to be paid on construction contracts and construction management contracts shall be determined in accordance with the applicable profit/fee technique for such contracts set forth in 915.404-4-71.
(b) Profit and fee to be paid on contracts under the threshold stated at 48 CFR 15.403-4(a)(1), not using the weighted guidelines, shall be judgmentally developed by the contracting officer by assigning individual dollar amounts to the factors appropriate to DOE profit considerations discussed in 915.404-4-70-2(d).
(c) Contracts which require only delivery or furnishing of goods or services supplied by subcontractors shall include a fee or profit which, in the best judgment of the contracting officer, is appropriate. It would be expected that there would be a declining relationship of profit/fee dollars in relation to total costs. The higher the cost of subcontracts, for example, the lower the profit/fee ratio to these costs.
(d) Profit/Fee considerations in termination settlements are often a question of equity. They are a matter of negotiation. They should not, however, exceed what would have otherwise been payable under weighted guidelines had the termination not occurred.