14.201 Preparation of invitations for bids.
14.202 Uniform contract format.
14.202-2 Part II Contract clauses.
14.202-3 Part III Documents, exhibits, and other attachments.
14.202-4 Part IV Representations and instructions.
14.204 Economic purchase quantities (supplies).
14.206 Descriptive literature.
14.207 Solicitation Provisions.
14.211 Two-Step Sealed Bidding.
Subpart 14.3 - Evaluation and award
14.301 Submission, modification, or withdrawal of bids.
14.302 Receipt of an unreadable electronic bid.
14.304-2 Apparent clerical mistakes.
14.304-3 Other mistakes disclosed before award.
14.305 Cancellation of invitations after opening.
14.306-1 Responsiveness of bids.
14.306-2 Responsible bidder—reasonableness of price.
14.306-3 Rejection of individual bids.
14.306-4 Rejection of all bids.
14.306-5 Restrictions on disclosure of descriptive literature.
14.306-6 All or none qualifications.
14.306-7 Minor informalities or irregularities in bids.
14.306-8 Prompt payment discounts.
14.306-9 Economic price adjustment.
14.308 Award of equal low bids.
14.309 Information to bidders.
14.309-1 Award of unclassified contracts.
14.000 Scope of part.
This part prescribes (a) the basic requirements of contracting for supplies and services (including construction) by sealed bidding, (b) the information to be included in the invitation for bids (IFB), (c) procedures concerning the submission of bids, (d) requirements for opening, evaluating bids, awarding contracts, and (e) procedures for two-step sealed bidding.
Subpart 14.1 - General
(a) Sealed bidding is a method of contracting that employs competitive bids, public opening of bids, and awards.
(b) Use sealed bidding whenever the conditions in 6.101(b) are met.
(c) The contracting officer must use firm-fixed-price contracts when using sealed bidding or fixed-price contracts with economic price adjustment clauses when some flexibility is necessary and feasible.
Subpart 14.2 - Presolicitation
14.201 Preparation of invitations for bids.
14.201-1 Format.
(a)Contracting officers must prepare invitation for bids and contracts using parts I, II, III, and IV of the uniform contract format (see part 15) to the maximum practicable extent.
(b) The uniform contract format is not required when contracting for—
(1) Construction (see part 36);
(2) Shipbuilding (including design, construction, and conversion), ship overhaul, and ship repair;
(3) Subsistence items;
(4) Supplies or services requiring special contract forms prescribed elsewhere in this regulation that are inconsistent with the uniform contract format; or
(5) Firm-fixed-price or fixed-price with economic price adjustment acquisitions that use the simplified contract format.
(c) The contracting officer may use the simplified contract format in lieu of the uniform contract format.
(1) The contracting officer has flexibility in preparation and organization of the simplified contract format. The following format should be used to the maximum extent practical:
(i) Use Standard Form (SF) 1447, Solicitation/Contract, as the first page of the IFB.
(ii) Include the following for each line item:
(A) Line item number.
(B) Description of supplies or services, or data sufficient to identify the requirement.
(C) Quantity and unit of issue.
(D) Unit price and amount.
(E) Packaging and marking requirements.
(F) Inspection and acceptance, quality assurance, and reliability requirements.
(G) Place of delivery, performance and delivery dates, period of performance, and f.o.b. point.
(H) Other item-peculiar information as necessary (e.g., individual fund citations).
(iii) Include the clauses required by this regulation. Additional clauses must be incorporated only when necessary to the particular acquisition.
(iv) List of documents and attachments (include if necessary).
(v) Representations and instructions:
(A) Insert the IFB provisions that require representations, certifications, or the submission of other information by offerors.
(B) Insert the IFB provisions required by 14.207. Include any other information/instructions necessary to guide offerors.
(C) Insert all price related evaluation factors and any significant price related subfactors for award.
(D) Upon award, the contracting officer must retain the representations and instructions in the contract file.
14.202 Uniform contract format.
14.202-1 Part I Schedule.
The contracting officer shall prepare the Schedule as follows:
(a) Section A, Solicitation/contract form.
(1) For sealed bidding the SF 33 or the SF 1447 may be used. When the SF 1447 is used as the IFB document, insert the information in subdivisions (a)(2)(i) and (a)(2)(iv) of this section in block 9 of the SF 1447.
(2) If the SF 33 or the SF 1447 are not used, include the following on the first page of the invitation for bids:
(i) Name, address, and location of issuing activity, including room and building where bids must be submitted.
(ii) Invitation for bids number.
(iii) Date of issuance.
(iv) Time specified for receipt of bids.
(v) Number of pages.
(vi) Requisition or other purchase authority.
(vii) Requirement for a bidder to provide its name and complete address, including street, city, county, State, and ZIP code.
(viii) A statement that bidders should include in the bid the address to which payment should be mailed, if that address is different from that of the bidder.
(b) Section B, Supplies or services and prices.
(1) See 15.108-1(b)
(2) Optional Form 336 (OF 336), Continuation Sheet, may be used.
(c) Section C, Description/specifications. (see 15.108-1(c)).
(d) Section D, Packaging and marking (see 15.108-1(d)).
(e) Section E, Inspection and acceptance (see 15.108-1(e)).
(f) Section F, Deliveries or performance (see 15.108-1(f)).
(g) Section G, Contract administration data (see 15.108-1(g)).
(h) Section H, Special contract requirements (see 15.108-1(h)).
14.202-2 Part II Contract clauses.
Section I, Contract clauses (see 15.108-2).
14.202-3 Part III Documents, exhibits, and other attachments.
Section J, List of documents, exhibits, and other attachments (see 15.108-3).
14.202-4 Part IV Representations and instructions.
The contracting officer shall prepare the representations and instructions as follows:
(a)Section K, Representations, certifications, and other statements of bidders (see 15.108-4(a)).
(b) Section L, Instructions, conditions, and notices to bidders (see 15.108-4(b)). The contracting officer must include the time and place for bid openings.
(c) Section M, Evaluation factors for award (see 15.108-4(c)).
14.203 Requirements.
(a)An IFB must clearly, accurately, and completely describe the Government requirements.
(b) Restrictive specifications or requirements that might unduly limit the number of bidders are prohibited.
(c) Include all documents and information (whether attached or incorporated by reference) prospective bidders will need for the purpose of bidding.
(d) The contracting officer must state in the invitation for bids that bids will be evaluated without discussions (see 52.214-10 and, for construction contracts, 52.214-19).
(e) When considering establishing qualification requirements, see and follow subpart 9.2.
14.204 Economic purchase quantities (supplies).
Contracting officers must comply with the economic purchase quantity planning requirements for supplies in part 7. See part 7 for instructions regarding use of the provision at 52.207-4, Economic Purchase Quantity—Supplies, and for guidance on handling responses to that provision.
14.205 Bid samples.
(a)The contracting officer must not require bidders to furnish bid samples unless—
(1) Characteristics of the product cannot be described adequately in the specification or purchase description;
(2) Necessary to determine the responsiveness of the bid. Do not use samples to determine a bidder's ability to produce the required items; and
(3) Products must be suitable from the standpoint of balance, facility of use, general “feel”, color, pattern, or other characteristics that cannot be described adequately in the specification.
(b) If the contracting officer requires bid samples, the IFB must state—
(1) The number and, if appropriate, size, and description of the bid samples required; and
(2) List all the characteristics for which the bid samples will be examined.
(c)
(1) Contracting officers may waive bid sample requirements when a bidder offers a product previously or currently contracted for or tested by the Government and found to comply with specification requirements conforming in every material respect with those in the current invitation for bids. (See 14.207(j)(2)).
(2) Where samples required by a Federal, Military, or other formal specification are not considered necessary and a waiver of the sample requirements of the specification is, include a statement in the invitation that notwithstanding the requirements of the specification, samples are not required.
(d) Bid samples furnished with a bid that are not required by the invitation generally will not be considered as qualifying the bid and will be disregarded. However, the bid sample will not be disregarded if it is clear from the bid or accompanying papers that the bidder's intention was to qualify the bid. If the qualification does not conform to the IFB, see 14.306-3(d).
(e)
(1) Return samples that are not destroyed in testing to bidders at their request and expense, unless otherwise specified in the invitation.
(2) Request disposition instructions from bidders.
(3) Samples are ordinarily returned collect to the address from which received if disposition instructions are not received within 30 days. Small items may be returned by mail, postage prepaid.
(4) Transmit samples that are intended for inspection purposes in connection with deliveries to the inspecting activity concerned, with instructions to retain the sample until completion of the contract or until disposition instructions are furnished.
(5) Where samples are consumed or their usefulness is impaired by tests, dispose as scrap unless the bidder requests their return.
14.206 Descriptive literature.
(a)Contracting officers must not require bidders to furnish descriptive literature unless it is needed before award to determine whether the products offered meet the specification and to establish exactly what the bidder proposes to furnish.
(b) The contracting officer must document in the contract file the justification why product acceptability cannot be determined without the submission of descriptive literature, except when the contract specifications require submission.
(c)
(1) If the invitation will require descriptive literature, the IFB must clearly state—
(i) What descriptive literature the bidders must furnish;
(ii) The purpose for requiring the literature;
(iii) The extent of its consideration in the evaluation of bids; and
(iv) The rules that will apply if a bidder fails to furnish the literature before bid opening or if the literature provided does not comply with the requirements of the invitation.
(2) If bidders must furnish descriptive literature, see 14.207(k).
(d)
(1) The contracting officer may waive the requirement for descriptive literature if—
(i) The bidder states in the bid that the product being offered is the same as a product previously or currently being furnished to the contracting activity; and
(ii) The contracting officer determines that the product offered complies with the specification requirements of the current invitation for bids. When the contracting officer waives the requirement, see 14.207(k)(2).
(2) When descriptive literature is not necessary and a waiver of literature requirements of a specification has been authorized, the contracting officer must include a statement in the invitation that, despite the requirements of the specifications, descriptive literature is not required.
(3) If the IFB provides for a waiver, a bidder may submit a bid on the basis of either the descriptive literature furnished with the bid or a previously furnished product. If the bid is submitted on one basis, the bidder may not have it considered on the other basis after bids are opened.
(e) If descriptive literature is furnished when it is not required by the invitation for bids, follow the procedures at 14.205(d).
14.207 Solicitation Provisions.
(a)The provisions prescribed in this section apply to preparation and submission of bids in general. See other FAR parts for provisions and clauses related to specific acquisition requirements.
(b) Insert in all invitations for bids the provisions at—
(1) 52.214-3, Amendments to Invitations for Bids; and
(2) 52.214-4, False Statements in Bids.
(3) 52.214-5, Submission of Bids.
(4) 52.214-6, Explanation to Prospective Bidders.
(5) 52.214-7, Late Submissions, Modifications, and Withdrawals of Bids.
(c) Insert in all invitations for bids, except those for construction, the provision at 52.214-10, Contract Award-Sealed Bidding.
(d) Insert in invitations for bids to which the uniform contract format applies, the provision at 52.214-12, Preparation of Bids.
(e) Insert the provision at 52.214-14, Place of Performance—Sealed Bidding, in invitations for bids except those in which the place of performance is specified by the Government.
(f) Insert the provision at 52.214-15, Period for Acceptance of Bids, in invitations for bids (IFB's) that are not issued on SF 33 or SF 1447 except IFB's—
(1) For construction work or
(2) In which the Government specifies a minimum acceptance period.
(g) Insert the provision at 52.214-16, Minimum Bid Acceptance Period, in invitations for bids, except for construction, if the contracting officer determines that a minimum acceptance period must be specified.
(h) Insert the provision at 52.214-18, Preparation of Bids—Construction, in invitations for bids for construction work.
(i) Insert the provision at 52.214-19, Contract Award—Sealed Bidding—Construction, in all invitations for bids for construction work.
(j)
(1) Insert the provision at 52.214-20, Bid Samples, in invitations for bids if bid samples are required.
(2) If it appears that the conditions in 14.205(c)(1) will apply and the contracting officer anticipates granting waivers and—
(i) If the nature of the required product does not necessitate limiting the grant of a waiver to a product produced at the same plant in which the product previously acquired or tested was produced, use the provision with its Alternate I; or
(ii) If the nature of the required product necessitates limiting the grant of a waiver to a product produced at the same plant in which the product previously acquired or tested was produced, use the provision with its Alternate II.
(3) See 14.205(c)(2) regarding waiving the requirement for all bidders.
(k)
(1) Insert the provision at 52.214-21, Descriptive Literature, in invitations for bids if—
(i) Descriptive literature is required to evaluate the technical acceptability of an offered product and
(ii) The required information will not be readily available unless it is submitted by bidders.
(2) Use the basic clause with its Alternate I if the possibility exists that the contracting officer may waive the requirement for furnishing descriptive literature for a bidder offering a previously supplied product that meets specification requirements of the current IFB.
(3) See 14.206(d)(2) regarding waiving the requirement for all bidders.
(l) Insert the provision at 52.214-22, Evaluation of Bids for Multiple Awards, in invitations for bids if the contracting officer determines that multiple awards might be made if doing so is economically advantageous to the Government.
(m) Insert the provision at 52.214-23, Late Submissions, Modifications, Revisions, and Withdrawals of Technical Proposals under Two-Step Sealed Bidding, in solicitations for technical proposals in step one of two-step sealed bidding.
(n) Insert the provision at 52.214-24, Multiple Technical Proposals, in solicitations for technical proposals in step one of two-step sealed bidding if the contracting officer permits the submission of multiple technical proposals.
(o) Insert the provision at 52.214-25, Step Two of Two-Step Sealed Bidding, in invitations for bids issued under step two of two-step sealed bidding.
(p) Insert the provision at 52.214-34, Submission of Offers in the English Language, in solicitations that include any of the clauses prescribed in part 25. It may be included in other solicitations when the contracting officer decides that it is necessary.
(q) Insert the provision at 52.214-35, Submission of Offers in U.S. Currency, in solicitations that include any of the clauses prescribed in part 25, unless the contracting officer includes the clause at 52.225-17, Evaluation of Foreign Currency Offers, as prescribed in part 25. It may be included in other solicitations when the contracting officer decides that it is necessary.
14.208 Contract clauses.
(a)Insert the clause at 52.214-26, Audit and Records-Sealed Bidding, in solicitations and contracts if the contract amount is expected to exceed the threshold at part 15 for submission of certified cost or pricing data.
(b)
(1) Insert the clause at 52.214-27, Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding, in solicitations and contracts if the contract amount is expected to exceed the threshold for submission of certified cost or pricing data at part 15.
(2) In exceptional cases, the head of the contracting activity may waive the requirement for inclusion of the clause in a contract with a foreign government or agency of that government. The authorizations for the waiver and the reasons for granting it must be in writing.
(c) Insert the clause at 52.214-28, Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding, in solicitations and contracts if the contract amount is expected to exceed the threshold for submission of certified cost or pricing data at part 15; or
(1) Upon request of a contractor in connection with a prime contract entered into before July 1, 2018, the contracting officer must modify the contract without requiring consideration to replace clause 52.214-28, Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding, with its Alternate I.
(2) In exceptional cases, the head of the contracting activity may waive the requirement for inclusion of the clause in a contract with a foreign government or agency of that government. The authorizations for the waiver and the reasons for granting it must be in writing.
(d) Insert the clause at 52.214-29, Order of Precedence—Sealed Bidding, in solicitations and contracts to which the uniform contract format applies.
14.209 Soliciting bids.
(a)See subpart 5.1 for presolicitation notices.
(b) See subpart 5.2 for publicizing the IFB.
(c) The contracting officer must specify in the IFB whether bids will be accepted by paper submission, or electronic transmission method, or both.
(d) If the IFB has been issued and it becomes necessary to make changes in quantity, specifications, delivery schedules, opening dates, etc., or to make a correction, such changes must be accomplished by amendment of the IFB using Standard Form 30, Amendment of Solicitation/ Modification of Contract. Amendments must—
(1) Be issued before the time set for bid opening;
(2) If determined necessary by the contracting officer, consider the amount of time remaining until bid opening and the need for an extension to the bid opening date;
(3) Be published in the GPE, if the IFB was published in the GPE, as a solicitation amendment;
(4) If applicable, be displayed in the bid room;
(5) Provide all prospective bidders equal access to the amendment providing the information necessary to submit bids; and
(6) Require acknowledgment of each amendment within each bidder’s bid.
(e) When electronic bids are specified, the contracting officer must include in the IFB the acceptable methods and the necessary information that allows bidders to submit bids that are compatible with Government systems.
(f) When a contracting office is located in the United States, any IFB sent to a prospective bidder located outside the United States must be sent by electronic data interchange or air mail if security classification permits.
(g)
(1) The master IFB is provided to potential sources who are requested to retain it for continued and repetitive use.
(2) Subsequent individual IFB must reference the date of the current master IFB and identify any changes.
(3) When using a master IFB the contracting officer must—
(i) Make available copies of the master IFB on request; and
(ii) Provide the cognizant contract administration activity a current copy of the master IFB.
(h) Retain records of invitations for bids and records of bids as a record of each invitation a contracting office issues and each abstract or record of bids. The file for each invitation must show the—
(1) Distribution that was made;
(2) Date the invitation was issued; and
(3) Names and addresses of prospective bidders who requested the invitation and were not included on the original IFB list must be added to the list and made a part of the record.
(i) See subpart 15.201 for policy on the release of acquisition information before and after the issuance of the IFB.
(j) An IFB may be cancelled by the contracting officer when clearly in the public interest; e.g.,
(1) Where there is no longer a requirement for the supplies or services; or
(2) Where amendments to the IFB would be of such magnitude that a new IFB is desirable.
(k) If an IFB is cancelled prior to the date and time specified in 14.301, the contracting officer must—
(1) Identify the IFB number and short title or subject matter;
(2) Briefly explain the reason for the cancellation; and
(3) Where appropriate, assure prospective bidders that they will be given an opportunity to bid on any resolicitation of bids or any future requirements for the type of supplies or services involved. Cancellations must be recorded in accordance with 14.303(g).
14.210 Submission of Bids.
(a) Allow prospective bidders a reasonable time to prepare and submit bids in response to all invitations, consistent with the needs of the Government.
(b) Provide at least 30 calendar days when a synopsis is required (see subpart 5.1).
(c) Require bidders to submit sealed bids to be opened publicly at the time and place stated in the IFB.
14.211 Two-Step Sealed Bidding.
14.211-1 General.
Two-step sealed bidding is a combination of competitive procedures designed to obtain the benefits of sealed bidding when adequate specifications are not available. An objective is to permit the development of a sufficiently descriptive and not unduly restrictive statement of the Government's requirements, including an adequate technical data package, so that subsequent acquisitions may use conventional sealed bidding methods. This two-step method is especially useful in acquisitions requiring technical proposals, particularly those for complex items.
Step one consists of the request for submission of technical proposals, evaluation, and (if necessary) discussion of a technical proposal. No pricing is submitted with step one. The objective is to determine the acceptability of the supplies or services offered. As used in this context, the word technical has a broad connotation and includes, among other things, the engineering approach, special manufacturing processes, and special testing techniques. It is the proper step for clarification of questions relating to technical requirements. Conformity to the technical requirements is resolved in this step, but not responsibility as defined in 9.
Step two involves the submission of sealed priced bids by those who submitted acceptable technical proposals in step one. Bids submitted in step two are evaluated and the awards made in accordance with subpart 14.3.
14.211-2 Conditions for use.
(a)Unless other factors require the use of sealed bidding, the contracting officer may use two-step sealed bidding rather than negotiation when all of the following conditions are present:
(1) Available specifications or purchase descriptions are not definite or complete or may be too restrictive without technical evaluation, and any necessary discussion, of the technical aspects of the requirement to ensure mutual understanding between each source and the Government.
(2) Definite criteria exist for evaluating technical proposals.
(3) More than one technically qualified source is expected to be available.
(4) There is sufficient time to use the two-step method.
(5) The contracting officer intends to award a firm-fixed-price contract or a fixed-price contract with economic price adjustment.
(b) None of the following precludes the use of two-step sealed bidding:
(1) Multi-year contracting.
(2) Government property to be made available to the successful bidder.
(3) A total small business set-aside (see part 19).
(4) The use of a set-aside or price evaluation preference for HUBZone small business concerns (see part 19).
(5) The use of a set-aside for service-disabled veteran-owned small business concerns (see part 19).
(6) The use of a set-aside for economically disadvantaged women-owned small business concerns and women-owned small business concerns eligible under the Women-Owned Small Business Program (see part 19).
14.211-3 Procedures.
(a) Step one.
(1) Synopsize requests for technical proposals in accordance with Part 5. The request must include, as a minimum, the following:
(i) A description of the supplies or services required.
(ii) A statement of intent to use the two-step method.
(iii) The requirements of the technical proposal.
(iv) The evaluation criteria, to include all factors and any significant subfactors.
(v) A statement that the technical proposals must not include prices or pricing information.
(vi) The date, or date and hour, by which the technical proposal must be received (see 14.210).
(vii) A statement that, in the second step—
(A) The contracting officer will consider awards based upon bids that have acceptable technical proposals, either initially or as a result of discussions; and
(B) Each technical proposal must be based on the bidder's own technical proposals.
(viii) A statement that—
(A) Bidders should submit technical proposals that are acceptable without additional explanation or information;
(B) The Government may make a final determination regarding a technical proposal's acceptability solely on the basis as submitted; and
(C) The Government may proceed with the second step without requesting further information from any bidder; however, the Government may request additional information from bidders of bids that it considers reasonably susceptible of being made acceptable and may discuss bids with their bidders.
(ix) A statement that a notice of unacceptability will be forwarded to the bidder upon completion of the technical proposal evaluation and final determination of unacceptability.
(x) A statement either that each bidder may only submit one technical proposal or, if authorized, multiple technical proposals. When specifications permit different technical approaches, it is generally in the Government's interest to authorize multiple technical proposals. If multiple technical proposals are authorized, see 14.207(n).
(2) Include information on delivery or performance requirements that may assist bidders in determining whether or not to submit a technical proposal. Indicate that the information is not binding on the Government and that the invitation issued under step two will include actual delivery or performance requirements.
(3) Upon receipt, the contracting officer must—
(i) Safeguard technical proposals against disclosure to unauthorized persons;
(ii) Accept and handle data marked in accordance with part 15 and 27; and
(iii) Remove any reference to price or cost.
(4) The contracting officer must establish a time period for evaluating technical proposals. The period may vary with the complexity and number of technical proposals involved. However, the evaluation should be completed quickly.
(5)
(i) Base evaluations on the criteria in the request for proposals but not consideration of responsibility as defined in part 9. Categorize technical proposals as—
(A) Acceptable;
(B) Reasonably susceptible of being made acceptable; or
(C) Unacceptable.
(ii) Categorize any proposal that modifies, or fails to conform to the essential requirements or specifications of, the request for technical proposals as unacceptable.
(6)
(i) The contracting officer may proceed directly with step two if there are sufficient acceptable proposals to ensure adequate price competition under step two, and if further time, effort and delay to make additional technical proposals acceptable and thereby increase competition would not be in Government's interest. If this is not the case, the contracting officer must request bidders whose technical proposals may be made acceptable to submit additional clarifying or supplementing information. The contracting officer must identify the nature of the deficiencies in the technical proposal or the nature of the additional information required. The contracting officer may also arrange discussions for this purpose. Do not discuss a technical proposal with any bidder other than the submitter.
(ii) When requesting additional information, the contracting officer must establish an appropriate time for bidders to conclude discussions, if any, submit all additional information, and incorporate such additional information as part of their technical proposals. The contracting officer may extend the due date for such submissions at their discretion. If the additional information is incorporated into a technical proposal within the established time, and the contracting officer determines that the technical proposal is acceptable, the contracting officer will update its category to acceptable.
(7) When a technical proposal is found unacceptable (either initially or after clarification), the contracting officer must promptly notify the bidder of the basis of the determination and that a revision of the technical proposal will not be considered. Upon written request, the contracting officer must debrief unsuccessful bidders (see part 15).
(8) Late technical proposals are governed by part 15.
(9) If it is necessary to discontinue two-step sealed bidding, the contracting officer must include a statement of the facts and circumstances in the contract file. The contracting officer must notify each bidder in writing. When step one results in no acceptable technical proposals or only one acceptable technical proposal, the acquisition may be continued by negotiation.
(b) Step two.
(1) Follow sealed bidding procedures except that invitations for bids in step two must—
(i) Be issued only to those bidders that submitted acceptable technical proposals in step one;
(ii) Include the provision prescribed in 14.207(o);
(iii) Clearly state that the bidder must comply with the specifications and the bidder's technical proposal; and
(iv) Not be synopsized through the Governmentwide point of entry (GPE) as an acquisition opportunity nor publicly posted.
(2) List the names of firms that submitted acceptable proposals in step one through the GPE for the benefit of prospective subcontractors (see 5.201).
Subpart 14.3 - Evaluation and award
14.301 Submission, modification, or withdrawal of bids.
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals not later than the exact time set for opening of bids. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b) Bids may be modified or withdrawn by any method authorized by the IFB.
(c) The receiving official receiving a paper bid submission, modification or withdrawal must—
(1) Write on the envelope—
(i) The date and time of receipt and by whom; and
(ii) The invitation for bid number; and
(2) Sign the envelope.
(3) Not disclose bid information before the time set for bid opening. See part 3 for requirements for protecting information including access to and disclosure thereof.
(d) A bidder or its authorized representative may withdraw a paper bid submission in person if, before the exact time set for opening of bids, the identity of the persons requesting withdrawal is established and that person signs a receipt for the bid.
(e) A bidder may withdraw an electronically submitted bid if notice is received in the office designated in the IFB not later than the exact time set for opening of bids. Upon withdrawal of an electronically transmitted bid, the data received must not be viewed and, to the maximum extent practical, must be purged from primary and backup data storage systems.
(f)
(1) Any bid, modification, or withdrawal of a bid received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless—
(i) It is received before award is made; and
(ii) The contracting officer determines that accepting the late bid would not unduly delay the acquisition; and—
(A) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(B) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) The contracting officer will consider and may accept, a late modification of an otherwise successful bid, that makes its terms more favorable to the Government, at any time it is received.
(g) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(h) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB, and urgent Government requirements preclude amendment of the bid opening date, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the IFB on the first work day on which normal Government processes resume.
(i) The contracting officer must promptly notify any bidder if its bid, modification, or withdrawal was received late, and must inform the bidder whether its bid will be considered, unless contract award is imminent, and the notices prescribed in 14.309 would suffice.
(j) Late bids and modifications that are not considered must be held unopened, unless opened for identification, until after award and then retained with other unsuccessful bids. However, any bid bond or guarantee must be returned.
(k) If available, the following must be included in the contract files for each late bid, modification, or withdrawal:
(1) The date and hour of receipt.
(2) A statement, with supporting rationale, regarding whether the bid was considered for award.
(3) The envelope, wrapper, or other evidence of the date of receipt.
14.302 Receipt of an unreadable electronic bid.
If a bid received at the Government facility by electronic data interchange is unreadable to the degree that conformance to the essential requirements of the invitation for bids cannot be ascertained, the contracting officer must immediately notify the bidder that the bid will be rejected unless the bidder provides clear and convincing evidence—
(a) Of the content of the bid as originally submitted; and
(b) That the unreadable condition of the bid was caused by Government software or hardware error, malfunction, or other Government mishandling.
14.303 Bid opening.
(a) All bids (including modifications) received before the time set for the opening of bids must be secured in a locked bid box, a safe, or in a secure restricted-access electronic bid box (i.e., secure password protected file folder on a controlled access Government computer network).
(b) The bid opening officer must inform those present at the public bid opening that the time set for the opening of bids has arrived.
(c)
(1) The bid opening officer must personally and publicly open all bids received before the exact time set for opening of bids and if practical, read the bids aloud to all present.
(1) The public may not attend bid openings for classified acquisitions. No public record must be made of bids or bid prices received in response to classified invitations for bids.
(d) The contracting officer may postpone the public bid opening if the contracting officer determines in writing there is reason to believe—
(1) An important segment of bidders has been delayed in the mail;
(2) That there are delays in the communications system specified for transmission of bids;
(3) That circumstances beyond the control of the bidders have delayed their timely submission, (e.g., flood, fire, accident, weather, strikes, or Government equipment blackout or malfunction); or
(4) That emergency or unanticipated events has interrupted normal Governmental processes so that the scheduled opening of bids is impractical.
(e) Publicly post a determination to postpone a bid opening under paragraph (d) of this section. If practical before issuance of a formal amendment of the invitation, communicate the determination to the prospective bidders likely to attend the scheduled bid opening.
(f) In the case of paragraph (d)(4) of this section, and when urgent Government requirements preclude amendment of the IFB, the time specified for opening of bids will be deemed to be extended to the same time of day specified in the IFB on the first workday on which normal Government processes resume. In such cases, the time of actual bid opening must be deemed to be the time set for bid opening for the purpose of determining “late bids” under section 14.301. A note should be made on the abstract of bids or otherwise added to the file explaining the circumstances of the postponement.
(g) The bid opening officer must complete and certify the accuracy of the Standard Form 1409, Abstract of Offers, or Optional Form 1419, Abstract of Offers—Construction (or automated equivalent) as soon after bid opening as practicable. Where bid items are too numerous to warrant complete recording of all bids, abstract entries for individual bids may be limited to item numbers and bid prices. The contracting activity may use the extra columns and SF 1410, Abstract of Offers—Continuation, and OF 1419A, Abstract of Offers—Construction, Continuation Sheet, to label and record such information as necessary.
(h) Abstracts of offers for unclassified acquisitions must be available for public inspection
14.304 Mistakes in bids.
14.304-1 General.
(a) After the opening of bids, contracting officers must examine all bids for mistakes.
(b) The authority to permit correction of bids is limited to bids that, as submitted, are responsive to the invitation. The authority does not permit correction of bids to make them responsive.
(c) If the contracting officer identifies an apparent mistake or has reason to believe that a mistake exists the contracting officer must request the bidder verify its bid, calling attention to the suspected mistake.
(d) If the bidder asserts a mistake in its bid, the matter must be processed in accordance with section 14.304. Such actions must be taken before award.
14.304-2 Apparent clerical mistakes.
(a) The contracting officer may correct any clerical mistake, apparent on its face in the bid, before award. The contracting officer first must obtain from the bidder a verification of the bid intended. Examples of apparent mistakes are obvious—
(1) Misplacement of a decimal point;
(2) Incorrect discounts (for example, 1 percent 10 days, 2 percent 20 days, 5 percent 30 days);
(3) Reversal of the price f.o.b. destination and price f.o.b. origin; and
(4) Mistake in designation of unit.
14.304-3 Other mistakes disclosed before award.
(a) A bidder may request in writing permission from the contracting officer to correct a mistake after providing clear and convincing evidence that establishes both the existence of the mistake, and the bid actually intended.
(1) If the contracting officer accepts the clear and convincing evidence and the correction does not cause the bidder to outbid other lower bids, the contracting officer may allow the correction.
(2) If the correction causes the bidder to outbid one or more otherwise lower bids, the head of the agency may make a determination to permit the correction only if the mistake and intended bid are obvious from the final bid documents.
(b) If a bidder requests permission to withdraw a bid rather than correct it, the evidence is clear and convincing both as to the existence of a mistake and as to the bid actually intended, and the bid, both as uncorrected and as corrected, is the lowest received, the head of the agency may make a determination to correct the bid and not permit its withdrawal.
(c) If, under paragraph (a) or (b) of this section—
(1) The evidence of a mistake is clear and convincing only as to the mistake but not as to the intended bid, or
(2) The evidence reasonably supports the existence of a mistake but is not clear and convincing, an official above the contracting officer, unless otherwise provided by agency procedures, may make a determination permitting the bidder to withdraw the bid.
(d) If the evidence does not warrant a determination under paragraph (a), (b), or (c) above, the head of the agency may make a determination that the bid be neither withdrawn nor corrected.
(e) Heads of agencies may delegate their authority to make the determinations under paragraphs (a), (b), (c), and (d) of this section to a central authority, or a limited number of authorities as necessary, in their agencies, without power of redelegation.
(f) Before issuance of the determinations in this section, legal counsel within the respective agency must provide concurrence.
(g) Process Government suspected or alleged mistakes in bids as follows:
(1) A mere statement by the administrative officials that they are satisfied that an error was made is insufficient.
(2) The contracting officer must immediately request that the bidder verify its bid.
(i) Actions taken to verify bids must be sufficient to reasonably assure the contracting officer that the bid as confirmed is without error, or to elicit the allegation of a mistake by the bidder.
(ii) To assure that the bidder will be put on notice of a suspected mistake by the contracting officer, the bidder should be advised as appropriate—
(A) That its bid is so much lower than the other bids or the Government's estimate as to indicate a possibility of error;
(B) Of important or unusual characteristics of the specifications;
(C) Of changes in requirements from previous purchases of a similar item; or
(D) Of any other information, proper for disclosure, that leads the contracting officer to believe that there is a mistake in bid.
(3) If the bid is verified, the contracting officer must consider the bid as originally submitted.
(4) If the time for acceptance of bids is likely to expire before a decision can be made, the contracting officer must request all bidders whose bids may become eligible for award to extend the time for acceptance of their bids.
(5) If the bidder whose bid is believed erroneous does not (or cannot) grant an extension of time, the bid must be considered as originally submitted (but see paragraph (8) below).
(6) If the bidder alleges a mistake, the contracting officer must advise the bidder to make a written request to withdraw or modify the bid. The request must be supported by statements (sworn statements, if possible) and must include all pertinent evidence such as the bidder’s file copy of the bid, the original worksheets and other data used in preparing the bid, subcontractors’ quotations, if any, published price lists, and any other evidence that establishes the existence of the error, the manner in which it occurred, and the bid actually intended.
(7) When the bidder furnishes evidence supporting an alleged mistake, the contracting officer must refer the case to the appropriate authority together with the following data:
(i) A signed copy of the bid involved.
(ii) A copy of the invitation for bids and any specifications or drawings relevant to the alleged mistake.
(iii) An abstract or record of the bids received.
(iv) The bidder’s written request to withdraw or modify the bid, together with the bidder's written statement and supporting evidence.
(v) A written statement by the contracting officer providing—
(A) A description of the supplies or services involved;
(B) The expiration date of the bid in question and of the other bids submitted;
(C) Specific information as to how and when the mistake was alleged;
(D) A summary of the evidence submitted by the bidder;
(E) In the event only one bid was received, a quotation of the most recent contract price for the supplies or services involved or, in the absence of a recent comparable contract, the contracting officer's estimate of a fair price for the supplies or services;
(F) Any additional pertinent evidence; and
(G) A recommendation to consider the bid as submitted or to authorize the bidder to withdraw or modify its bid.
(8) Where the bidder fails or refuses to furnish evidence in support of a suspected or alleged mistake, the contracting officer must consider the bid as submitted unless—
(i) The amount of the bid is so far out of line with the amounts of other bids received, or with the amount estimated by the agency or determined by the contracting officer to be reasonable; or
(ii) There are other indications of error which are so clear, as to reasonably justify the conclusion that acceptance of the bid would be unfair to the bidder or to other bona fide bidders. The contracting officer must document all attempts made to obtain the information required and the action taken with respect to the correct the bid.
(h) Each agency must maintain records of all determinations made in accordance with this section, the facts involved, and the action taken in each case. Include copies of all such determinations in the file.
(i) Nothing contained in this section prevents an agency from submitting doubtful cases to the Comptroller General for advance decision.
14.305 Cancellation of invitations after opening.
(a) Unless there is a compelling reason to reject all bids and cancel the invitation after the opening, the contracting officer must award to the responsible bidder who submitted the lowest responsive bid.
(b) Invitations may be cancelled after opening when, consistent with paragraph (a) above and, the agency head determines in writing that—
(1) Inadequate or ambiguous specifications were cited in the invitation;
(2) Specifications have been revised;
(3) The supplies or services being contracted for are no longer required;
(4) The invitation did not provide for consideration of all factors of cost to the Government, such as cost of transporting Government-furnished property to bidders' plants;
(5) Bids received indicate that the needs of the Government can be satisfied by a less expensive article differing from that for which the bids were invited;
(6) All otherwise acceptable bids received are at unreasonable prices, or only one bid is received and the contracting officer cannot determine the reasonableness of the bid price;
(7) The bids were not independently arrived at in open competition, were collusive, or were submitted in bad faith (see part 3 for reports to be made to the Department of Justice);
(8) No responsive bid has been received from a responsible bidder;
(9) A cost comparison as prescribed in OMB Circular A-76 shows that performance by the Government is more economical; or
(10) For other reasons, cancellation is clearly in the public's interest.
(c) If award is delayed beyond the bidders' acceptance periods, the contracting officer should request bidders extend in writing the bid acceptance period (with consent of sureties, if any) in order to avoid the need for resoliciting.
(d) Under some circumstances, completion of the acquisition after cancellation of the invitation for bids may be appropriate.
(1) If the invitation for bids has been cancelled for the reasons specified in paragraphs (b)(6) through (8) of this section, and the agency head has authorized, in the determination in paragraph (b) of this section, the completion of the acquisition through negotiation, the contracting officer must proceed in accordance with paragraph (e) of this section.
(2) If the invitation for bids has been cancelled for the reasons specified in paragraphs (b) (1), (2), (4), (5), or (10) of this section, or for the reasons in paragraphs (b) (6), (7), or (8) of this section and completion through negotiation is not authorized under paragraph (d)(1) of this section, the contracting officer must proceed with a new acquisition.
(e) When the agency head has determined, in accordance with paragraph (d)(1) of this section, that an invitation for bids should be canceled and that use of negotiation is in the Government's interest, the contracting officer may negotiate (in accordance with part 15, as appropriate) and make award without issuing a new IFB provided—
(1) Each responsible bidder in the sealed bid acquisition has been given notice that negotiations will be conducted and has been given an opportunity to participate in negotiations; and
(2) The award is made to the responsible bidder offering the lowest negotiated price.
14.306 Evaluation.
14.306-1 Responsiveness of bids.
(a) To be considered for award, a bid must comply in all material respects with the invitation for bids.
(b) Bids must be filled out, executed, and submitted in accordance with the instructions in the invitation. If a bidder uses its own bid form or a letter to submit a bid, the bid may be considered only if—
(1) The bidder accepts all the terms and conditions of the invitation; and
(2) Award on the bid would result in a binding contract with terms and conditions that do not vary from the terms and conditions of the invitation.
(c) Bids submitted by electronic commerce may be considered only if the electronic commerce method was specifically stipulated or permitted by the IFB.
(d) If any sample fails to conform to the characteristics listed in the invitation, the respective bid will be rejected as nonresponsive.
14.306-2 Responsible bidder—reasonableness of price.
(a) Prior to award, the contracting officer must determine that—
(1) The apparent awardee(s) is responsible (see subpart 9.1); and
(2) The prices offered are reasonable and not materially unbalanced.
(b) The price analysis techniques in part 15 should be used as guidelines for determining reasonableness and if prices offered are materially unbalanced.
(c) In each case the determination must be made in the light of all prevailing circumstances. Particular care must be taken in cases where only a single bid is received.
14.306-3 Rejection of individual bids.
(a) Bids that fail to conform to the basic requirements of the invitation for bids must be rejected.
(b) Bids that do not conform to the requirements must be rejected unless the invitation authorized the submission of alternate bids and the supplies offered as alternates meet the requirements specified in the invitation.
(c) Bids that fail to conform to the delivery schedule or permissible alternates stated in the invitation must be rejected.
(d) Bids must be rejected if the bidder imposes conditions that would modify requirements of the invitation or limit the bidder's liability to the Government. For example, bids must be rejected in which the bidder—
(1) Protects against future changes in conditions, such as increased costs, if total possible costs to the Government cannot be determined;
(2) Fails to state a price and indicates that price will be the price in effect at time of delivery;
(3) States a price but qualifies it as being subject to the price in effect at time of delivery;
(4) When not authorized by the invitation, conditions or qualifies a bid by stipulating that it is to be considered only if, before date of award, the bidder receives (or does not receive) award under a separate IFB;
(5) Requires the Government to determine that the bidder's product meets applicable Government specifications; or
(6) Limits rights of the Government under any contract clause.
(e) A low bidder may be requested to delete objectionable conditions from a bid provided the conditions do not go to the substance, as distinguished from the form, of the bid, or work an injustice on other bidders. A condition goes to the substance of a bid where it affects price, quantity, quality, or delivery of the items offered.
(f) The contracting officer may reject any bid if they determine in writing that it is unreasonable as to the total price of the bid or the prices for individual line items as well.
(g) The contracting officer may reject any bid if the prices for any line items or subline items are materially unbalanced (see part 15).
(h) The contracting officer must reject any bid received from a person or concern that is suspended, debarred, proposed for debarment, or declared ineligible as of the bid opening date unless determined in writing that there is a compelling reason for such action (see subpart 9.4).
(i) Reject low bids received from concerns determined to be not responsible pursuant to part 9, unless received from a small business concern (see part 19 with respect to certificates of competency).
(j) Reject a bid when a bid guarantee is required and a bidder fails to furnish the guarantee in accordance with the requirements of the invitation for bids, except as otherwise provided in part 28.
(k) Preserve the originals of all rejected bids, and any written findings with respect to such rejections with the contract file.
(l) After submitting a bid, if all of a bidder's assets or that part related to the bid are transferred during the period between the bid opening and the award, the transferee may not be able to take over the bid. Accordingly, the contracting officer must reject the bid unless the transfer is effected by merger, operation of law, or other means not barred by 41 U.S.C. 6305 or 31 U.S.C. 3727.
14.306-4 Rejection of all bids.
When it is determined necessary to reject all bids, the contracting officer must notify each bidder that all bids have been rejected and provide the reason for such action.
14.306-5 Restrictions on disclosure of descriptive literature.
When a bid is accompanied by descriptive literature, and the bidder imposes a restriction that prevents the public disclosure of such literature, the restriction may render the bid nonresponsive. The restriction renders the bid nonresponsive if it prohibits the disclosure of sufficient information to permit competing bidders to know the essential nature and type of the products offered or those elements of the bid that relate to quantity, price, and delivery terms. The provisions of this paragraph do not apply to unsolicited descriptive literature submitted by a bidder if such literature does not qualify the bid.
14.306-6 All or none qualifications.
Unless the IFB provides otherwise, a bid may be responsive notwithstanding that the bidder specifies that award will be accepted only on all, or a specified group, of the items. Contracting officers must not permit bidders to withdraw or modify all or none qualifications after bid opening since such qualifications are substantive and affect the rights of other bidders.
14.306-7 Minor informalities or irregularities in bids.
A minor informality or irregularity is merely a matter of form and not of substance or some immaterial defect in a bid or variation of a bid from the exact requirements of the invitation that can be corrected or waived without being prejudicial to other bidders. The defect or variation is immaterial when the effect on price, quantity, quality, or delivery is negligible when contrasted with the total cost or scope of the supplies or services being acquired. The contracting officer either must give the bidder an opportunity to cure any deficiency resulting from a minor informality or irregularity in a bid or waive the deficiency, whichever is to the advantage of the Government. Examples of minor informalities or irregularities include failure of a bidder to—
(a) Return the number of copies of signed bids required by the invitation;
(b) Furnish required information concerning the number of its employees;
(c) Sign its bid, but only if—
(1) The unsigned bid is accompanied by other material indicating the bidder's intention to be bound by the unsigned bid (such as the submission of a bid guarantee or a letter signed by the bidder, with the bid, referring to and clearly identifying the bid itself); or
(2) The firm submitting a bid has formally adopted or authorized, before the date set for opening of bids, the execution of documents by written, printed, or stamped signature and submits evidence of such authorization and the bid carries such a signature;
(d) Acknowledge receipt of an amendment to an invitation for bids, but only if—
(1) The bid received clearly indicates that the bidder received the amendment, such as where the amendment added another item to the invitation and the bidder submitted a bid on the item; or
(2) The amendment involves only a matter of form or has either no effect or merely a negligible effect on price, quantity, quality, or delivery of the item bid upon; and
(e) Execute the representations with respect to Equal Opportunity and Affirmative Action Programs, as set forth in the clauses at 52.222-22, Previous Contracts and Compliance Reports, and 52.222-25, Affirmative Action Compliance.
14.306-8 Prompt payment discounts.
Prompt payment discounts must not be considered in the evaluation of bids.
14.306-9 Economic price adjustment.
(a)Bidder proposed economic price adjustment.
(1) When an IFB does not contain an economic price adjustment clause but a bidder proposes one with a ceiling that the price will not exceed, the contracting officer must evaluate the bid on the basis of the maximum possible economic price adjustment of the quoted base price.
(2) If the bid is eligible for award, the contracting officer must request the bidder to agree to the inclusion in the award of an approved economic price adjustment clause (see part 16) that is subject to the same ceiling. If the bidder will not agree to an approved clause, the contracting officer may award based on the bid as originally submitted.
(3) Reject bids that contain economic price adjustments with no ceiling unless a clear basis for evaluation exists.
(b)
(1) When an invitation contains a Government proposed economic price adjustment clause and no bidder takes exception to the provisions, the contracting officer must evaluate bids on the basis of the quoted prices without the allowable economic price adjustment being added.
(2) Reject a bid as nonresponsive if a bidder increases the maximum percentage of economic price adjustment stipulated in the invitation or limits the downward economic price adjustment provisions of the invitation.
(3) Reject a bid as nonresponsive if a bid indicates deletion of the economic price adjustment clause because the downward economic price adjustment provisions are thereby limited.
(4) When a bidder decreases the maximum percentage of economic price adjustment stipulated in the invitation, the contracting officer must evaluate the bid at the base price on an equal basis with bids that do not reduce the stipulated ceiling. However, after evaluation, if the bidder offering the lower ceiling is in a position to receive the award, the award must reflect the lower ceiling.
14.307 Award.
(a) The contracting officer must make a contract award—
(1) By written or electronic notice,
(2) Within the time for acceptance specified in the bid or an extension, and
(3) To that responsible bidder whose bid, conforming to the invitation, will be most advantageous to the Government, considering only price and the price-related factors included in the invitation.
(b) When more than one award results from any single invitation for bids, separate award documents must be executed.
(c) When an award is made to a bidder for less than all of the items that may be awarded to that bidder and additional items are being withheld for subsequent award, the invitation to bid and award document must state that the Government may make subsequent awards for those additional items within the bid acceptance period.
(d) All provisions of the invitation for bids, including any acceptable additions or changes made by a bidder in the bid, must be clearly and accurately set forth (either expressly or by reference) in the award document.
(e)
(1) Award is generally made by using the Award portion of Standard Form (SF) 33, Solicitation, Offer, and Award, or SF 1447, Solicitation/Contract (see 53.214). If an offer on an SF 33 leads to further changes, the resulting contract must be prepared as a bilateral document on SF 26, Award/Contract.
(2) Use of the Award portion of SF 33, SF 26, or SF 1447, does not preclude the additional use of informal documents, including electronic communications, as notices of awards.
(3) Do not physically include Part IV in the contract. Award by acceptance of a bid on the award portion of Standard Form 33, Solicitation Offer and Award (SF 33), Standard Form 26, Award/Contract (SF 26), or Standard Form 1447, Solicitation/Contract (SF 1447), incorporates Section K, Representations, certifications, and other statements of bidders, in the resultant contract even though not physically attached.
(f) Any discount offered will form a part of the award and will be taken by the payment center if payment is made within the discount period specified by the bidder.
(1) As an alternative to indicating a discount in conjunction with the offer, bidders may prefer to offer discounts on individual invoices.
14.308 Award of equal low bids.
(a) Award contracts in the following order of priority when two or more low bids are equal in all respects:
(1) Small business concerns that are also labor surplus area concerns.
(2) Other small business concerns.
(3) Other business concerns.
(b) If two or more bidders remain equally eligible after application of paragraph (a) above, the contracting officer must conduct a drawing, limited to those bidders. If time permits, give the bidders involved an opportunity to attend the drawing. The drawing must be witnessed by at least three persons, and the contract file must contain the names and addresses of the witnesses and the person supervising the drawing.
(c) When an award is to be made by using the priorities under this section, the contracting officer must include a written agreement in the contract that the contractor will perform, or cause to be performed, the contract in accordance with the circumstances justifying the priority used to break the tie or select bids for a drawing by lot.
14.309 Information to bidders.
14.309-1 Award of unclassified contracts.
(a) The contracting officer must as a minimum (subject to any restrictions in part 9)—
(1) Notify each unsuccessful bidder in writing or electronically within three days after contract award, that its bid was not accepted. “Day,” for purposes of the notification process, means calendar day, except that the period will run until a day which is not a Saturday, Sunday, or legal holiday; and
(2) When award is made to other than a low bidder, state the reason for rejection in the notice to each of the unsuccessful low bidders.
(b) For acquisitions covered by the World Trade Organization Government Procurement Agreement or a Free Trade Agreement (see part 25), agencies must include in notices given unsuccessful bidders from World Trade Organization Government Procurement Agreement or Free Trade Agreement countries—
(1) The dollar amount of the successful bid; and
(2) The name and address of the successful bidder.
14.309-2 Award of classified contracts.
In addition to 14.309-1, if classified information was furnished or created in connection with the IFB, the contracting officer must advise the unsuccessful bidders, including any who did not bid, to take disposition action in accordance with agency procedures. The contracting officer may provide the name of the successful bidder and the contract price to unsuccessful bidders upon request. Information regarding a classified award must not be provided by telephone.
Subpart 14.4 - Postaward.
14.401 Mistakes after award.
If a contractor's discovery and request for correction of a mistake in bid is not made until after the award, it must be processed under the procedures of part 33 and the following:
(a) When a mistake in a contractor's bid is not discovered until after award, correct the mistake by contract modification if it would be favorable to the Government without changing the essential requirements of the specifications.
(b) In addition to the cases contemplated in paragraph (a) of this section or as otherwise authorized by law, agencies are authorized to make a determination—
(1) To rescind a contract;
(2) To reform a contract to—
(i) Delete the items involved in the mistake; or
(ii) Increase the price if the contract price, as corrected, does not exceed that of the next lowest acceptable bid under the original invitation for bids; or
(3) That no change will be made in the contract as awarded, if the evidence does not warrant a determination under paragraphs (1) or (2).
(c) Make determinations under paragraphs (b)(1) and (2) on the basis of clear and convincing evidence that a mistake in bid was made. In addition, it must be clear that the mistake was—
(1) Mutual, or
(2) If unilaterally made by the contractor, so apparent as to have charged the contracting officer with notice of the probability of the mistake.
(d) Each proposed determination must be coordinated with legal counsel in accordance with agency procedures.
(e) Process mistakes alleged or disclosed after award as follows:
(1) The contracting officer must request the contractor to support the alleged mistake by submission of written statements and pertinent evidence, such as—
(i) The contractor's file copy of the bid,
(ii) The contractor's original worksheets and other data used in preparing the bid,
(iii) Subcontractors' and suppliers' quotations, if any,
(iv) Published price lists, and
(v) Any other evidence that will serve to establish the mistake, the manner in which the mistake occurred, and the bid actually intended.
(2) The case file concerning an alleged mistake must contain the following:
(i) All evidence furnished by the contractor in support of the alleged mistake.
(ii) A signed statement by the contracting officer—
(A) Describing the supplies or services involved;
(B) Specifying how and when the mistake was alleged or disclosed;
(C) Summarizing the evidence submitted by the contractor and any additional evidence considered pertinent;
(D) Quoting, in cases where only one bid was received, the most recent contract price for the supplies or services involved, or in the absence of a recent comparable contract, the contracting officer's estimate of a fair price for the supplies or services and the basis for the estimate;
(E) Setting forth the contracting officer's opinion whether a bona fide mistake was made and whether the contracting officer was, or should have been, on constructive notice of the mistake before the award, together with the reasons for, or data in support of, such opinion;
(F) Setting forth the course of action with respect to the alleged mistake that the contracting officer considers proper on the basis of the evidence, and if other than a change in contract price is recommended, the manner by which the supplies or services will otherwise be acquired; and
(G) Disclosing the status of performance and payments under the contract, including contemplated performance and payments.
(iii) A signed copy of the bid involved.
(iv) A copy of the invitation for bids and any specifications or drawings relevant to the alleged mistake.
(v) An abstract of written record of the bids received.
(vi) A written request by the contractor to reform or rescind the contract, and copies of all other relevant correspondence between the contracting officer and the contractor concerning the alleged mistake.
(vii) A copy of the contract and any related change orders or supplemental agreements.
(f) Each agency must include in the contract file a record of—
(1) All determinations made in accordance with this 14.401;
(2) the facts involved, and
(3) the action taken in each case.
14.402 Pricing modifications.
See part 15 for cost and price negotiation policies and procedures.
Feedback
We welcome informal input on the revised FAR :
Non-regulatory Resources
The following are non-regulatory resources associated with FAR :
FAR Companion Guide Coming Soon.
Caveat
The FAR Council created deviations will include clauses and provisions currently required by statute and Executive Order. OMB and the FAR Council will work with Congress to recommend statutory changes and with the White House to recommend rescission of requirements stemming from prior Executive Orders that are inconsistent with the goals of Executive Order 14275 to stop the inefficient use of American taxpayer dollars in federal procurement. Any changes to Executive Orders or statute will be reflected when the Revolutionary FAR Overhaul turns to rule-making.