PGI 211.273-3 Procedures.
(1) Solicitations for previously developed items shall encourage offerors to identify Single Process Initiative (SPI) processes for use instead of military or Federal specifications and standards cited in the solicitation. Use of the clause at DFARS 252.211-7005, Substitutions for Military or Federal Specifications and Standards, satisfies this requirement.
(2) Contracting officers shall ensure that—
(i) Concurrence of the requiring activity is obtained for any proposed substitutions prior to contract award;
(ii) Any necessary additional information regarding the SPI process identified in the proposal is obtained from the cognizant administrative contracting officer; and
(iii) In competitive procurements, prospective offerors are provided the opportunity to obtain verification that an SPI process is an acceptable replacement for a military or Federal specification or standard for the particular procurement prior to the date specified for receipt of offers.
(3) Any determination that an SPI process is not acceptable for a specific procurement shall be made prior to contract award at the head of the contracting activity or program executive officer level. This authority may not be delegated.