SOFARS PART 5606COMPETITION REQUIREMENTS



SOFARS PART 5606 - COMPETITION REQUIREMENTS
SUBPART 5606.3 - OTHER THAN FULL AND OPEN COMPETITION
5606.303 Justifications.

5606.303-90
Policy.
5606.303-90.1
Amended J&A (Changes/Increases/Decreases).
SUBPART 5606.5 - COMPETITION ADVOCATES
5606.501
Requirement.

SOFARS PART 5606
COMPETITION REQUIREMENTS

 

SUBPART 5606.3 - OTHER THAN FULL AND OPEN COMPETITION

5606.303 Justifications.


5606.303-90 Policy.
(Revised April 2008)
(a) When multiple sources are included in a class Justification and Approval (J&A) request, each source specified must be fully justified in accordance with FAR 6.303-2(a)(5).
(b) Only one of the statutory authorities provided by 10 U.S.C. 2304 will be cited in Paragraph 4 of the J&A. If another statutory authority applies that will strengthen the justification for other than full and open competition, it may be cited in Paragraph 8 of the J&A.
(c) A full scale J&A is not required for solicitations issued in accordance with FAR Part 13, however the justification must be documented in the contract file.
The J&A template can be found in the DCG.


5606.303-90.1 Amended J&A (Changes/Increases/Decreases).
(Revised June 2008)
(a) The Contracting Officer shall amend the J&A and obtain approval at the required level (Attachment 5601-1) prior to awarding the contract or issuing a modification if any of the following circumstances occur:

(1) Prior to award of the basic contract;
(i) The negotiated in-scope price increases by twenty-percent (20%) or more, or any increase in which the additional work/quantities were not originally contemplated in the J&A,
(ii) The negotiated price increase causes the approval level authority to rise to a higher level,
(iii) There is a change in the competitive strategy that would further reduce competition,
(iv) There is a change in the requirement that affects the basis for the justification.
(1) Actions occurring after award of the basic contract;
(i) There is an out of scope change to the work package,
(ii) There is a cost increase of twenty-percent (20%) or more, or any increase in which the additional work/quantities were not originally contemplated at award,
(iii) A cost increase causes the approval level authority to rise to a higher level.

(a) A document entitled, "Amendment to Justification and Approval for Other than Full and Open Competition," may be prepared in lieu of a new J&A using the same paragraph designations as the basic J&A. Paragraphs of the basic J&A not affected by the amendment should be annotated, "No Change." Multiple amendments should be numbered sequentially. The Contracting Officer shall submit a copy of the basic J&A along with the amended J&A to the appropriate approval level as listed in Attachment 5601-1.
(b) If the statutory authority for other than full and open competition is no longer applicable, or a different statutory authority now applies, a new J&A shall be completed.

SUBPART 5606.5 - COMPETITION ADVOCATES

5606.501 Requirement.
(Revised January 2009)
(a) The USSOCOM Acquisition Executive/Senior Procurement Executive (AE/SPE), delegates the duties of the USSOCOM Competition Advocate General (CAG) to the Deputy Director of Procurement, and the duties of the Component Competition Advocate to each Contracting Office Chief and Division Chief of SOAL-KH/KP/KW/K/KRI. These duties are not delegable.
(b)   In the absence of the Competition Advocate General, the Chief, Procurement Management Division (SOAL-KM) or Chief, Field Assistance Division (SOAL-KA), as appropriate, shall review J&A packages prior to submission to the AE/SPE for approval. However, the DOP shall sign the J&A as the acting CAG.

 
HQ, United States Special Operations Command
Special Operations Acquisition and Logistics Center (SOAL-K)
SOFARS 5606
February 2007