252.232-7000 Advance Payment Pool.
As prescribed in 232.412-70(a), use the following clause:
ADVANCE PAYMENT POOL (DEC 1991)
(a) Notwithstanding any other provision of this contract, advance payments will be made for contract performance in accordance with the Determinations, Findings, and Authorization for Advance payment dated __________________________.
(b) Payments made in accordance with this clause shall be governed by the terms and conditions of the Advance Payment Pool Agreement between the United States of America and (insert the name of the contractor). The Agreement is incorporated in the contract by reference.
(End of clause)
252.232-7001 Disposition of Payments.
As prescribed in 232.412-70(b), use the following clause:
DISPOSITION OF PAYMENTS (DEC 1991)
Payment will be by a dual payee Treasury check made payable to the contractor or the (insert the name of the disbursing office in the advance payment pool agreement), and will be forwarded to that disbursing office for appropriate disposition.
(End of clause)
252.232-7002 Progress Payments for Foreign Military Sales Acquisitions.
As prescribed in 232.502-4-70(a), use the following clause:
PROGRESS PAYMENTS FOR FOREIGN MILITARY SALES ACQUISITIONS
(DEC 1991)
If this contract includes foreign military sales (FMS) requirements, the Contractor shall—
(a) Submit a separate progress payment request for each progress payment rate; and
(b) Submit a supporting schedule showing—
(1) The amount of each request distributed to each country's requirements; and
(2) Total price per contract line item applicable to each separate progress payment rate.
(c) Identify in each progress payment request the contract requirements to which it applies (i.e., FMS or U.S.);
(d) Calculate each request on the basis of the prices, costs (including costs to complete), subcontractor progress payments, and progress payment liquidations of the contract requirements to which it applies; and
(e) Distribute costs among contract line items and countries in a manner acceptable to the Administrative Contracting Officer.
(End of clause)
Class Deviation 2019-O0002 (dtd 12/10/18) —Non-electronic Submission of Payment Requests for Packing, Crating, and Storage of Household Goods. Effective immediately this deviation remains in effect until March 31, 2020, or otherwise rescinded.
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. (See Class Deviation 2019-O0002)
As prescribed in 232.7004(a), use the following clause:
ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING
REPORTS (JUN 2012)
(a) Definitions. As used in this clause—
(1) “Contract financing payment” and “invoice payment” have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) “Electronic form” means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) “Payment request” means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) “Receiving report” means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when—
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer’s determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.
(End of clause)
252.232-7004 DoD Progress Payment Rates.
As prescribed in 232.502-4-70(b), use the following clause:
DOD PROGRESS PAYMENT RATES (OCT 2014)
If the Contractor is a small business concern, the Progress Payments clause of this contract is modified to change each mention of the progress payment rate and liquidation rate (excepting paragraph (k), Limitations on Undefinitized Contract Actions) to 90 percent.
(End of clause)
252.232-7005 Reimbursement of Subcontractor Advance Payments--DoD Pilot Mentor-Protege Program.
As prescribed in 232.412-70(c), use the following clause:
REIMBURSEMENT OF SUBCONTRACTOR ADVANCE PAYMENTS--DOD PILOT MENTOR-PROTEGE PROGRAM (SEP 2001)
(a) The Government will reimburse the Contractor for any advance payments made by the Contractor, as a mentor firm, to a protege firm, pursuant to an approved mentor-protege agreement, provided—
(1) The Contractor’s subcontract with the protege firm includes a provision substantially the same as FAR 52.232-12, Advance Payments;
(2) The Contractor has administered the advance payments in accordance with the policies of FAR Subpart 32.4; and
(3) The Contractor agrees that any financial loss resulting from the failure or inability of the protege firm to repay any unliquidated advance payments is the sole financial responsibility of the Contractor.
(b) For a fixed price type contract, advance payments made to a protege firm shall be paid and administered as if they were 100 percent progress payments. The Contractor shall include as a separate attachment with each Standard Form (SF) 1443, Contractor’s Request for Progress Payment, a request for reimbursement of advance payments made to a protege firm. The attachment shall provide a separate calculation of lines 14a through 14e of SF 1443 for each protege, reflecting the status of advance payments made to that protege.
(c) For cost reimbursable contracts, reimbursement of advance payments shall be made via public voucher. The Contractor shall show the amounts of advance payments made to each protege on the public voucher, in the form and detail directed by the cognizant contracting officer or contract auditor.
(End of clause)
252.232-7006 Wide Area WorkFlow Payment Instructions.
As prescribed in 232.7004(b), use the following clause:
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
___________________________________________________________
(Contracting Officer: Insert applicable document type(s).
Note: If a “Combo” document type is identified but not supportable by the Contractor’s business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
____________________________________________________________
(Contracting Officer: Insert inspection and acceptance locations or “Not applicable.”)
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF |
Data to be entered in WAWF |
Pay Official DoDAAC |
|
Issue By DoDAAC |
|
Admin DoDAAC |
|
Inspect By DoDAAC |
|
Ship To Code |
|
Ship From Code |
|
Mark For Code |
|
Service Approver (DoDAAC) |
|
Service Acceptor (DoDAAC) |
|
Accept at Other DoDAAC |
|
LPO DoDAAC |
|
DCAA Auditor DoDAAC |
|
Other DoDAAC(s) |
(*Contracting Officer: Insert applicable DoDAAC information or “See schedule”
if multiple ship to/acceptance locations apply, or “Not applicable.”)
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the e-mail address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
________________________________________________________________
(Contracting Officer: Insert applicable email addresses or “Not applicable.”)
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
_________________________________________________________________
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
(End of clause)
252.232-7007 Limitation of Government’s Obligation.
As prescribed in 232.705-70, use the following clause:
LIMITATION OF GOVERNMENT’S OBLIGATION (APR 2014)
(a) Contract line item(s) [Contracting Officer insert after negotiations] is/are incrementally funded. For this/these item(s), the sum of $ [Contracting Officer insert after negotiations] of the total price is presently available for payment and allotted to this contract. An allotment schedule is set forth in paragraph (j) of this clause.
(b) For item(s) identified in paragraph (a) of this clause, the Contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement in the event of termination of those item(s) for the Government’s convenience, approximates the total amount currently allotted to the contract. The Contractor is not authorized to continue work on those item(s) beyond that point. The Government will not be obligated in any event to reimburse the Contractor in excess of the amount allotted to the contract for those item(s) regardless of anything to the contrary in the clause entitled “Termination for Convenience of the Government.” As used in this clause, the total amount payable by the Government in the event of termination of applicable contract line item(s) for convenience includes costs, profit, and estimated termination settlement costs for those item(s).
(c) Notwithstanding the dates specified in the allotment schedule in paragraph (j) of this clause, the Contractor will notify the Contracting Officer in writing at least ninety days prior to the date when, in the Contractor’s best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 85 percent of the total amount then allotted to the contract for performance of the applicable item(s). The notification will state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of applicable line items up to the next scheduled date for allotment of funds identified in paragraph (j) of this clause, or to a mutually agreed upon substitute date. The notification will also advise the Contracting Officer of the estimated amount of additional funds that will be required for the timely performance of the item(s) funded pursuant to this clause, for a subsequent period as may be specified in the allotment schedule in paragraph (j) of this clause or otherwise agreed to by the parties. If after such notification additional funds are not allotted by the date identified in the Contractor’s notification, or by an agreed substitute date, the Contracting Officer will terminate any item(s) for which additional funds have not been allotted, pursuant to the clause of this contract entitled “Termination for Convenience of the Government.”
(d) When additional funds are allotted for continued performance of the contract line item(s) identified in paragraph (a) of this clause, the parties will agree as to the period of contract performance which will be covered by the funds. The provisions of paragraphs (b) through (d) of this clause will apply in like manner to the additional allotted funds and agreed substitute date, and the contract will be modified accordingly.
(e) If, solely by reason of failure of the Government to allot additional funds, by the dates indicated below, in amounts sufficient for timely performance of the contract line item(s) identified in paragraph (a) of this clause, the Contractor incurs additional costs or is delayed in the performance of the work under this contract and if additional funds are allotted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the item(s), or in the time of delivery, or both. Failure to agree to any such equitable adjustment hereunder will be a dispute concerning a question of fact within the meaning of the clause entitled “Disputes.”
(f) The Government may at any time prior to termination allot additional funds for the performance of the contract line item(s) identified in paragraph (a) of this clause.
(g) The termination provisions of this clause do not limit the rights of the Government under the clause entitled “Default.” The provisions of this clause are limited to the work and allotment of funds for the contract line item(s) set forth in paragraph (a) of this clause. This clause no longer applies once the contract is fully funded except with regard to the rights or obligations of the parties concerning equitable adjustments negotiated under paragraphs (d) and (e) of this clause.
(h) Nothing in this clause affects the right of the Government to terminate this contract pursuant to the clause of this contract entitled “Termination for Convenience of the Government.”
(i) Nothing in this clause shall be construed as authorization of voluntary services whose acceptance is otherwise prohibited under 31 U.S.C. 1342.
(j) The parties contemplate that the Government will allot funds to this contract in accordance with the following schedule:
On execution of contract |
$ ________ |
(month) (day), (year) |
$ ________ |
(month) (day), (year) |
$ ________ |
(month) (day), (year) |
$ ________ |
(End of clause)
252.232-7008 Assignment of Claims (Overseas).
As prescribed in 232.806(a)(1), use the following clause:
ASSIGNMENT OF CLAIMS (OVERSEAS) (JUN 1997)
(a) No claims for monies due, or to become due, shall be assigned by the Contractor unless
(1) Approved in writing by the Contracting Officer;
(2) Made in accordance with the laws and regulations of the United States of America; and
(3) Permitted by the laws and regulations of the Contractor’s country.
(b) In no event shall copies of this contract or of any plans, specifications, or other similar documents relating to work under this contract, if marked “Top Secret,” “Secret,” or “Confidential” be furnished to any assignee of any claim arising under this contract or to any other person not entitled to receive such documents. However, a copy of any part or all of this contract so marked may be furnished, or any information contained herein may be disclosed, to such assignee upon the Contracting Officer’s prior written authorization.
(c) Any assignment under this contract shall cover all amounts payable under this contract and not already paid, and shall not be made to more than one party, except that any such assignment may be made to one party as agent or trustee for two or more parties participating in such financing. On each invoice or voucher submitted for payment under this contract to which any assignment applies, and for which direct payment thereof is to be made to an assignee, the Contractor shall
(1) Identify the assignee by name and complete address; and
(2) Acknowledge the validity of the assignment and the right of the named assignee to receive payment in the amount invoiced or vouchered.
(End of clause)
252.232-7009 Mandatory Payment by Governmentwide Commercial Purchase Card.
As prescribed in 232.1110, use the following clause:
MANDATORY PAYMENT BY GOVERNMENTWIDE COMMERCIAL PURCHASE
CARD (MAY 2018)
The Contractor agrees to accept the Governmentwide commercial purchase card as the method of payment for orders or calls valued at or below the micro-purchase threshold
in part 202 of the Defense Federal Acquisition Regulation Supplement, under this
contract or agreement.
(End of clause)
252.232-7010 Levies on Contract Payments.
As prescribed in 232.7102, use the following clause:
LEVIES ON CONTRACT PAYMENTS (DEC 2006)
(a) 26 U.S.C. 6331(h) authorizes the Internal Revenue Service (IRS) to continuously levy up to 100 percent of contract payments, up to the amount of tax debt.
(b) When a levy is imposed on a payment under this contract and the Contractor believes that the levy may result in an inability to perform the contract, the Contractor shall promptly notify the Procuring Contracting Officer in writing, with a copy to the Administrative Contracting Officer, and shall provide—
(1) The total dollar amount of the levy;
(2) A statement that the Contractor believes that the levy may result in an inability to perform the contract, including rationale and adequate supporting documentation; and
(3) Advice as to whether the inability to perform may adversely affect national security, including rationale and adequate supporting documentation.
(c) DoD shall promptly review the Contractor’s assessment, and the Procuring Contracting Officer shall provide a written notification to the Contractor including–
(1) A statement as to whether DoD agrees that the levy may result in an inability to perform the contract; and
(2)(i) If the levy may result in an inability to perform the contract and the lack of performance will adversely affect national security, the total amount of the monies collected that should be returned to the Contractor; or
(ii) If the levy may result in an inability to perform the contract but will not impact national security, a recommendation that the Contractor promptly notify the IRS to attempt to resolve the tax situation.
(d) Any DoD determination under this clause is not subject to appeal under the Contract Disputes Act.
(End of clause)
252.232-7011 Payments in Support of Emergencies and Contingency Operations.
As prescribed in 232.908, use the following clause:
PAYMENTS IN SUPPORT OF EMERGENCIES AND CONTINGENCY
OPERATIONS (MAY 2013)
(a) Definitions of pertinent terms are set forth in sections 2.101, 32.001, and 32.902 of the Federal Acquisition Regulation.
(b) Notwithstanding any other payment clause in this contract, the Government will make invoice payments under the terms and conditions specified in this clause. The Government considers payment as being made on the day a check is dated or the date of an electronic funds transfer.
(c) Invoice payments.
(1) Due date.
(i) Payment will be made as soon as possible once a proper invoice is received and matched with the contract and the receiving/acceptance report.
(ii) If the contract does not require submission of an invoice for payment (e.g., periodic lease payments), the due date will be as specified in the contract.
(2) Contractor's invoice. The Contractor shall prepare and submit invoices to the designated billing office specified in the contract. A proper invoice should include the items listed in paragraphs (c)(2)(i) through (c)(2)(x) of this clause.
(i) Name and address of the Contractor.
(ii) Invoice date and invoice number. (The Contractor should date invoices as close as possible to the date of the mailing or transmission.)
(iii) Contract number or other authorization for supplies delivered or services performed (including order number and contract line item number).
(iv) Description, quantity, unit of measure, unit price, and extended price of supplies delivered or services performed.
(v) Shipping and payment terms (e.g., shipment number and date of shipment, discount for prompt payment terms). Bill of lading number and weight of shipment will be shown for shipments on Government bills of lading.
(vi) Name and address of Contractor official to whom payment is to be sent (must be the same as that in the contract or in a proper notice of assignment).
(vii) Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.
(viii) Taxpayer Identification Number (when required). The taxpayer identification number is required for all payees subject to the U.S. Internal Revenue Code.
(ix) Electronic funds transfer banking information.
(A) The Contractor shall include electronic funds transfer banking information on the invoice only if required elsewhere in this contract.
(B) If electronic funds transfer banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct electronic funds transfer banking information in accordance with the applicable solicitation provision (e.g., FAR 52.232-38, Submission of Electronic Funds Transfer Information with Offer), contract clause (e.g., FAR 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or FAR 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.
(C) Electronic funds transfer banking information is not required if the Government waived the requirement to pay by electronic funds transfer.
(x) Any other information or documentation required by the contract (e.g., evidence of shipment).
(3) Discounts for prompt payment. The designated payment office will take cost-effective discounts if the payment is made within the discount terms of the contract.
(4) Contract financing payment. If this contract provides for contract financing, the Government will make contract financing payments in accordance with the applicable contract financing clause.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment, including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected contract line item or subline item, if applicable; and
(D) Contractor point of contact; and
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(d) This clause is applicable until otherwise notified by the Contracting Officer. Upon notification by issuance of a contract modification, the appropriate FAR Prompt Payment clause in the contract becomes applicable.
(End of clause)
252.232-7012 Performance-Based Payments–Whole-Contract Basis.
As prescribed in 232.1005-70(a), use the following clause:
PERFORMANCE-BASED PAYMENTS-WHOLE-CONTRACT BASIS (MAR 2014)
(a) Performance-based payments shall form the basis for the contract financing payments provided under this contract, and shall apply to the whole contract. The performance-based payments schedule (Contract Attachment ____) describes the basis for payment, to include identification of the individual payment events, evidence of completion, and amount of payment due upon completion of each event.
(b)(i) At no time shall cumulative performance-based payments exceed cumulative contract cost incurred under this contract. To ensure compliance with this requirement, the Contractor shall, in addition to providing the information required by FAR 52.232-32, submit supporting information for all payment requests using the following format:
Current performance-based payment(s) event(s) addressed by this request: | ||
Contractor shall identify— |
Amount |
Totals |
(1a) Negotiated value of all previously completed performance-based payment(s) event(s); |
||
(1b) Negotiated value of the current performance-based payment(s) event(s); |
||
(1c) Cumulative negotiated value of performance-based payment(s) events completed to date (1a) + (1b); |
||
(2) Total costs incurred to date; |
||
(3) Enter the amount from (1c) or (2), whichever is less; |
||
(4) Cumulative amount of payments previously requested; and |
||
(5) Payment amount requested for the current performance-based payment(s) event(s) (3) - (4). |
(ii) The Contractor shall not submit payment requests more frequently than monthly.
(iii) Incurred cost is determined by the Contractor’s accounting books and records, which the contractor shall provide access to upon request of the Contracting Officer for the administration of this clause.
(End of clause)
252.232-7013 Performance-Based Payments—Deliverable-Item Basis.
As prescribed in 232.1005-70(b), use the following clause:
PERFORMANCE-BASED PAYMENTS-DELIVERABLE-ITEM BASIS (APR 2014)
(a) Performance-based payments shall form the basis for the contract financing payments provided under this contract and shall apply to Contract Line Item Numbers (CLIN(s)) _[Contracting Officer insert applicable CLIN(s)]_. The performance-based payments schedule (Contract Attachment ____) describes the basis for payment, to include identification of the individual payment events, CLINs to which each event applies, evidence of completion, and amount of payment due upon completion of each event.
(b)(i) At no time shall cumulative performance-based payments exceed cumulative contract cost incurred under CLIN(s) __[Contracting Officer insert applicable
CLIN(s)]__. To ensure compliance with this requirement, the Contractor shall, in
addition to providing the information required by FAR 52.232-32, submit supporting information for all payment requests using the following format:
Current performance-based payment(s) event(s) addressed by this request: | ||
Contractor shall identify— |
Amount |
Totals |
(1a) Negotiated value of all previously completed performance-based payment(s) event(s); |
||
(1b) Negotiated value of the current performance-based payment(s) event(s); |
||
(1c) Cumulative negotiated value of performance-based payment(s) event(s) completed to date (1a) + (1b); |
||
(2) Total costs incurred to date; |
||
(3) Enter the amount from (1c) or (2), whichever is less; |
||
(4) Cumulative amount of payments previously requested; and |
||
(5) Payment amount requested for the current performance-based payment(s) event(s) (3) - (4). |
(ii) The Contractor shall not submit payment requests more frequently than monthly.
(iii) Incurred cost is determined by the Contractor’s accounting books and records, which the contractor shall provide access to upon request of the Contracting Officer for the administration of this clause.
(End of clause)
252.232-7014 Notification of Payment in Local Currency (Afghanistan).
As prescribed in 232.7202, use the following provision:
NOTIFICATION OF PAYMENT IN LOCAL CURRENCY
(AFGHANISTAN) (SEP 2014)
(a) The contract resulting from this solicitation will be paid in Afghani (local currency) if the contract is awarded to a host nation vendor (Afghan), pursuant to the authority of USCENTCOM Fragmentary Order (FRAGO) 09-1567 and FRAGO 10-143. Contract payment will be made in Afghani (local currency) via electronic funds transfer (EFT) to a local (Afghan) banking institution, unless an exception in paragraph (c) applies. Contracts shall not be awarded to host nation vendors who do not bank locally. If award is made to other than a host nation vendor, the contract will be awarded in U.S. dollars.
(b) Vendors shall submit quotations and offers in U.S. dollars. If the contract is awarded to an Afghan vendor, the quotation or offer will be converted to Afghani using a Government budget rate of [Insert current budget rate here.] Afghani per U.S. dollar.
(c) By exception, the following forms of payment are acceptable, in the following order of priority, when the local finance office determines that EFT using ITS.gov is not available:
(1) EFT using Limited Depository Account (LDA).
(2) Check from the local finance office LDA.
(3) Local currency cash payments in Afghani (must be approved in writing by the local finance office and contracting office prior to contract award). Payments in cash are restricted to contracts when—
(i) The vendor provides proof via a letter from the host nation banking institution that it is not EFT capable; and
(ii) The local finance office validates that the vendor’s banking institution is not EFT capable. Cash payments will be made in Afghani.
(End of provision)
252.233-7001 Choice of Law (Overseas).
As prescribed in 233.215-70, use the following clause:
CHOICE OF LAW (OVERSEAS) (JUN 1997)
This contract shall be construed and interpreted in accordance with the substantive laws of the United States of America. By the execution of this contract, the Contractor expressly agrees to waive any rights to invoke the jurisdiction of local national courts where this contract is performed and agrees to accept the exclusive jurisdiction of the United States Armed Services Board of Contract Appeals and the United States Court of Federal Claims for the hearing and determination of any and all disputes that may arise under the Disputes clause of this contract.
(End of clause)
(Revised June 26, 2015)
252.234-7001 Notice of Earned Value Management System.
As prescribed in 234.203(1), use the following provision:
NOTICE OF EARNED VALUE MANAGEMENT SYSTEM (APR 2008)
(a) If the offeror submits a proposal in the amount of $50,000,000 or more—
(1) The offeror shall provide documentation that the Cognizant Federal Agency (CFA) has determined that the proposed Earned Value Management System (EVMS) complies with the EVMS guidelines in the American National Standards Institute/Electronic Industries Alliance Standard 748, Earned Value Management Systems (ANSI/EIA-748) (current version at time of solicitation). The Government reserves the right to perform reviews of the EVMS when deemed necessary to verify compliance.
(2) If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a)(1) of this provision, the offeror shall submit a comprehensive plan for compliance with the guidelines in ANSI/EIA-748.
(i) The plan shall—
(A) Describe the EVMS the offeror intends to use in performance of the contract, and how the proposed EVMS complies with the EVMS guidelines in ANSI/EIA-748;
(B) Distinguish between the offeror’s existing management system and modifications proposed to meet the EVMS guidelines;
(C) Describe the management system and its application in terms of the EVMS guidelines;
(D) Describe the proposed procedure for administration of the EVMS guidelines as applied to subcontractors; and
(E) Describe the process the offeror will use to determine subcontractor compliance with ANSI/EIA-748.
(ii) The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan.
(iii) The offeror’s EVMS plan must provide milestones that indicate when the offeror anticipates that the EVMS will be compliant with the guidelines in ANSI/EIA-748.
(b) If the offeror submits a proposal in an amount less than $50,000,000—
(1) The offeror shall submit a written description of the management procedures it will use and maintain in the performance of any resultant contract to comply with the requirements of the Earned Value Management System clause of the contract. The description shall include—
(i) A matrix that correlates each guideline in ANSI/EIA-748 (current version at time of solicitation) to the corresponding process in the offeror’s written management procedures; and
(ii) The process the offeror will use to determine subcontractor compliance with ANSI/EIA-748.
(2) If the offeror proposes to use an EVMS that has been determined by the CFA to be in compliance with the EVMS guidelines in ANSI/EIA-748, the offeror may submit a copy of the documentation of such determination instead of the written description required by paragraph (b)(1) of this provision.
(c) The offeror shall identify the subcontractors (or the subcontracted effort if subcontractors have not been selected) to whom the EVMS requirements will apply. The offeror and the Government shall agree to the subcontractors or the subcontracted effort selected for application of the EVMS requirements. The offeror shall be responsible for ensuring that the selected subcontractors comply with the requirements of the Earned Value Management System clause of the contract.
(End of provision)
252.234-7002 Earned Value Management System.
As prescribed in 234.203(2), use the following clause:
EARNED VALUE MANAGEMENT SYSTEM (MAY 2011)
(a) Definitions. As used in this clause——
“Acceptable earned value management system” means an earned value management system that generally complies with system criteria in paragraph (b) of this clause.
“Earned value management system” means an earned value management system that complies with the earned value management system guidelines in the ANSI/EIA-748.
“Significant deficiency” means a shortcoming in the system that materially affects the ability of officials of the Department of Defense to rely upon information produced by the system that is needed for management purposes.
(b) System criteria. In the performance of this contract, the Contractor shall use—
(1) An Earned Value Management System (EVMS) that complies with the EVMS guidelines in the American National Standards Institute/Electronic Industries Alliance Standard 748, Earned Value Management Systems (ANSI/EIA-748); and
(2) Management procedures that provide for generation of timely, reliable, and verifiable information for the Contract Performance Report (CPR) and the Integrated Master Schedule (IMS) required by the CPR and IMS data items of this contract.
(c) If this contract has a value of $50 million or more, the Contractor shall use an EVMS that has been determined to be acceptable by the Cognizant Federal Agency (CFA). If, at the time of award, the Contractor’s EVMS has not been determined by the CFA to be in compliance with the EVMS guidelines as stated in paragraph (b)(1) of this clause, the Contractor shall apply its current system to the contract and shall take necessary actions to meet the milestones in the Contractor’s EVMS plan.
(d) If this contract has a value of less than $50 million, the Government will notmake a formal determination that the Contractor’s EVMS complies with the EVMS guidelines in ANSI/EIA-748 with respect to the contract. The use of the Contractor’s EVMS for this contract does not imply a Government determination of the Contractor’s compliance with the EVMS guidelines in ANSI/EIA-748 for application to future contracts. The Government will allow the use of a Contractor’s EVMS that has been formally reviewed and determined by the CFA to be in compliance with the EVMS guidelines in ANSI/EIA-748.
(e) The Contractor shall submit notification of any proposed substantive changes to the EVMS procedures and the impact of those changes to the CFA. If this contract has a value of $50 million or more, unless a waiver is granted by the CFA, any EVMS changes proposed by the Contractor require approval of the CFA prior to implementation. The CFA will advise the Contractor of the acceptability of such changes as soon as practicable (generally within 30 calendar days) after receipt of the Contractor’s notice of proposed changes. If the CFA waives the advance approval requirements, the Contractor shall disclose EVMS changes to the CFA at least 14 calendar days prior to the effective date of implementation.
(f) The Government will schedule integrated baseline reviews as early as practicable, and the review process will be conducted not later than 180 calendar days after—
(1) Contract award;
(2) The exercise of significant contract options; and
(3) The incorporation of major modifications.
During such reviews, the Government and the Contractor will jointly assess the Contractor’s baseline to be used for performance measurement to ensure complete coverage of the statement of work, logical scheduling of the work activities, adequate resourcing, and identification of inherent risks.
(g) The Contractor shall provide access to all pertinent records and data requested by the Contracting Officer or duly authorized representative as necessary to permit Government surveillance to ensure that the EVMS complies, and continues to comply, with the performance criteria referenced in paragraph (b) of this clause.
(h) When indicated by contract performance, the Contractor shall submit a request for approval to initiate an over-target baseline or over-target schedule to the Contracting Officer. The request shall include a top-level projection of cost and/or schedule growth, a determination of whether or not performance variances will be retained, and a schedule of implementation for the rebaselining. The Government will acknowledge receipt of the request in a timely manner (generally within 30 calendar days).
(i) Significant deficiencies. (1) The Contracting Officer will provide an initial determination to the Contractor, in writing, of any significant deficiencies. The initial determination will describe the deficiency in sufficient detail to allow the Contractor to understand the deficiency.
(2) The Contractor shall respond within 30 days to a written initial determination from the Contracting Officer that identifies significant deficiencies in the Contractor's EVMS. If the Contractor disagrees with the initial determination, the Contractor shall state, in writing, its rationale for disagreeing.
(3) The Contracting Officer will evaluate the Contractor's response and notify the Contractor, in writing, of the Contracting Officer’s final determination concerning—
(i) Remaining significant deficiencies;
(ii) The adequacy of any proposed or completed corrective action;
(iii) System noncompliance, when the Contractor’s existing EVMS fails to comply with the earned value management system guidelines in the ANSI/EIA-748; and
(iv) System disapproval, if initial EVMS validation is not successfully completed within the timeframe approved by the Contracting Officer, or if the Contracting Officer determines that the Contractor's earned value management system contains one or more significant deficiencies in high-risk guidelines in ANSI/EIA-748 standards (guidelines 1, 3, 6, 7, 8, 9, 10, 12, 16, 21, 23, 26, 27, 28, 30, or 32). When the Contracting Officer determines that the existing earned value management system contains one or more significant deficiencies in one or more of the remaining 16 guidelines in ANSI/EIA-748 standards, the Contracting Officer will use discretion to disapprove the system based on input received from functional specialists and the auditor.
(4) If the Contractor receives the Contracting Officer’s final determination of significant deficiencies, the Contractor shall, within 45 days of receipt of the final determination, either correct the significant deficiencies or submit an acceptable corrective action plan showing milestones and actions to eliminate the significant deficiencies.
(j) Withholding payments. If the Contracting Officer makes a final determination to disapprove the Contractor’s EVMS, and the contract includes the clause at 252.242-7005, Contractor Business Systems, the Contracting Officer will withhold payments in accordance with that clause.
(k) With the exception of paragraphs (i) and (j) of this clause, the Contractor shall require its subcontractors to comply with EVMS requirements as follows:
(1) For subcontracts valued at $50 million or more, the following subcontractors shall comply with the requirements of this clause:
[Contracting Officer to insert names of subcontractors (or subcontracted effort if subcontractors have not been selected) designated for application of the EVMS requirements of this clause.]
(2) For subcontracts valued at less than $50 million, the following subcontractors shall comply with the requirements of this clause, excluding the requirements of paragraph (c) of this clause:
[Contracting Officer to insert names of subcontractors (or subcontracted effort if subcontractors have not been selected) designated for application of the EVMS requirements of this clause.]
(End of clause)
252.234-7003 Notice of Cost and Software Data Reporting System
Basic. As prescribed in 234.7101(a) and (a)(1), use the following provision:
NOTICE OF COST AND SOFTWARE DATA REPORTING SYSTEM—BASIC (NOV 2014)
(a) This solicitation includes—
(1) The Government-approved cost and software data reporting (CSDR) plan for the contract, DD Form 2794; and
(2) The related Resource Distribution Table.
(b) As part of its proposal, the Offeror shall—
(1) Describe the process to be used to satisfy the requirements of the DoD 5000.04-M-1, CSDR Manual, and the Government-approved CSDR plan for the proposed contract;
(2) Demonstrate how contractor cost and data reporting (CCDR) will be based, to the maximum extent possible, upon actual cost transactions and not cost allocations;
(3) Demonstrate how the data from its accounting system will be mapped into the standard reporting categories required in the CCDR data item descriptions;
(4) Describe how recurring and nonrecurring costs will be segregated;
(5) Provide comments on the adequacy of the CSDR contract plan and related Resource Distribution Table; and
(6) Submit the DD Form 1921, Cost Data Summary Report, and DD Form 1921–1, Functional Cost-Hour Report, with its pricing proposal.
(c) CSDR reporting will be required for subcontractors at any tier with a subcontract that exceeds $50 million. The offeror shall identify, by providing comments on the Resource Distribution Table, the subcontractors, or, if the subcontractors have not been selected, the subcontracted effort in this category.
(End of provision)
Alternate I. As prescribed in 234.7101(a) and (a)(2), use the following provision, which uses a different paragraph (c) than the basic provision:
NOTICE OF COST AND SOFTWARE DATA REPORTING SYSTEM—ALTERNATE I (NOV 2014)
(a) This solicitation includes—
(1) The Government-approved cost and software data reporting (CSDR) plan for the contract, DD Form 2794; and
(2) The related Resource Distribution Table.
(b) As part of its proposal, the Offeror shall—
(1) Describe the process to be used to satisfy the requirements of the DoD 5000.04-M-1, CSDR Manual, and the Government-approved CSDR plan for the proposed contract;
(2) Demonstrate how contractor cost and data reporting (CCDR) will be based, to the maximum extent possible, upon actual cost transactions and not cost allocations;
(3) Demonstrate how the data from its accounting system will be mapped into the standard reporting categories required in the CCDR data item descriptions;
(4) Describe how recurring and nonrecurring costs will be segregated;
(5) Provide comments on the adequacy of the CSDR contract plan and related Resource Distribution Table; and
(6) Submit the DD Form 1921, Cost Data Summary Report, and DD Form 1921–1, Functional Cost-Hour Report, with its pricing proposal.
(c) CSDR reporting will be required for subcontractors for selected subcontracts identified in the CSDR contract plan as requiring such reporting. The offeror shall identify, by providing comments on the Resource Distribution Table, the subcontractors, or, if the subcontractors have not been selected, the subcontracted effort.
(End of provision)
252.234-7004 Cost and Software Data Reporting System
Basic. As prescribed in 234.7101(b) and (b)(1), use the following clause:
COST AND SOFTWARE DATA REPORTING SYSTEM—BASIC (NOV 2014)
(a) In the performance of this contract, the Contractor shall use—
(1) A documented standard cost and software data reporting (CSDR) process that satisfies the guidelines contained in the DoD 5000.04–M–1, CSDR Manual;
(2) Management procedures that provide for generation of timely and reliable information for the contractor cost data reports (CCDRs) and software resources data reports (SRDRs) required by the CCDR and SRDR data items of this contract; and
(3) The Government-approved CSDR plan for this contract, DD Form 2794, and the related Resource Distribution Table as the basis for reporting in accordance with the required CSDR data item descriptions (DIDs).
(b) The Contractor shall require CSDR reporting from subcontractors at any tier with a subcontract that exceeds $50 million. If, for subcontracts that exceed $50 million, the Contractor changes subcontractors or makes new subcontract awards, the Contractor shall notify the Government.
(End of clause)
Alternate I. As prescribed in 234.7101(b) and (b)(2), use the following clause, which uses a different paragraph (b) than the basic clause:
COST AND SOFTWARE DATA REPORTING SYSTEM—ALTERNATE I (NOV 2014)
(a) In the performance of this contract, the Contractor shall use—
(1) A documented standard cost and software data reporting (CSDR) process that satisfies the guidelines contained in the DoD 5000.04–M–1, CSDR Manual;
(2) Management procedures that provide for generation of timely and reliable information for the contractor cost data reports (CCDRs) and software resources data reports (SRDRs) required by the CCDR and SRDR data items of this contract; and
(3) The Government-approved CSDR plan for this contract, DD Form 2794, and the related Resource Distribution Table as the basis for reporting in accordance with the required CSDR data item descriptions (DIDs).
(b) The Contractor shall require CSDR reporting from selected subcontractors identified in the CSDR contract plan as requiring such reporting. If the Contractor changes subcontractors or makes new awards for selected subcontract effort, the Contractor shall notify the Government.
(End of clause)
252.235-7000 Indemnification Under 10 U.S.C. 2354--Fixed Price.
As prescribed in 235.070-3, use the following clause:
INDEMNIFICATION UNDER 10 U.S.C. 2354--FIXED PRICE (DEC 1991)
(a) This clause provides for indemnification under 10 U.S.C. 2354 if the Contractor meets all the terms and conditions of this clause.
(b) Claims, losses, and damages covered—
(1) Claims by third persons for death, bodily injury, sickness, or disease, or the loss, damage, or lost use of property. Claims include those for reasonable expenses of litigation or settlement. The term “third persons” includes employees of the contractor;
(2) The loss, damage, and lost use of the Contractor's property, but excluding lost profit; and
(3) Loss, damage, or lost use of the Government's property.
(c) The claim, loss, or damage—
(1) Must arise from the direct performance of this contract;
(2) Must not be compensated by insurance or other means, or be within deductible amounts of the Contractor's insurance;
(3) Must result from an unusually hazardous risk as specifically defined in the contract;
(4) Must not result from willful misconduct or lack of good faith on the part of any of the Contractor's directors or officers, managers, superintendents, or other equivalent representatives who have supervision or direction of—
(i) All or substantially all of the Contractor's business;
(ii) All or substantially all of the Contractor's operations at any one plant or separate location where this contract is being performed; or
(iii) A separate and complete major industrial operation connected with the performance of this contract;
(5) Must not be a liability assumed under any contract or agreement (except for subcontracts covered by paragraph (h) of this clause), unless the Contracting Officer (or in contracts with the Department of the Navy, the Department) specifically approved the assumption of liability; and
(6) Must be certified as just and reasonable by the Secretary of the department or designated representative.
(d) The Contractor shall buy and maintain, to the extent available, insurance against unusually hazardous risks in the form, amount, period(s) of time, at the rate(s), and with such insurers, as the Contracting Officer (or, for Navy contracts, the Department) may from time to time require and approve. If the cost of this insurance is higher than the cost of the insurance the Contractor had as of the date of the contract, the Government shall reimburse the Contractor for the difference in cost, as long as it is properly allocable to this contract and is not included in the contract price. The Government shall not be liable for claims, loss, or damage if insurance was available and is either required or approved under this paragraph.
(e) A reduction of the insurance coverage maintained by the Contractor on the date of the execution of this contract shall not increase the Government's liability under this clause unless the Contracting Officer consents, and the contract price is equitably adjusted, if appropriate, to reflect the Contractor's consideration for the Government's assumption of increased liability.
(f) Notice. The Contractor shall—
(1) Promptly notify the Contracting Officer of any occurrence, action, or claim that might trigger the Government's liability under this clause;
(2) Furnish the proof or evidence of any claim, loss, or damage in the form and manner that the Government requires; and
(3) Immediately provide copies of all pertinent papers that the Contractor receives or has received.
(g) The Government may direct, participate in, and supervise the settlement or defense of the claim or action. The Contractor shall comply with the Government's directions and execute any authorizations required.
(h) Flowdown. The Government shall indemnify the Contractor if the Contractor has an obligation to indemnify a subcontractor under any subcontract at any tier under this contract for the unusually hazardous risk identified in this contract only if—
(1) The Contracting Officer gave prior written approval for the Contractor to provide in a subcontract for the Contractor to indemnify the subcontractor for unusually hazardous risks defined in this contract;
(2) The Contracting Officer approved those indemnification provisions;
(3) The subcontract indemnification provisions entitle the Contractor, or the Government, or both, to direct, participate in, and supervise the settlement or defense of relevant actions and claims; and
(4) The subcontract provides the same rights and duties, the same provisions for notice, furnishing of papers and the like, between the Contractor and the subcontractor, as exist between the Government and the Contractor under this clause.
(i) The Government may discharge its obligations under paragraph (h) of this clause by making payments directly to subcontractors or to persons to whom the subcontractors may be liable.
(j) The rights and obligations of the parties under this clause shall survive the termination, expiration, or completion of this contract.
(End of clause)
252.235-7001 Indemnification Under 10 U.S.C. 2354--Cost Reimbursement.
As prescribed in 235.070-3, use the following clause:
INDEMNIFICATION UNDER 10 U.S.C. 2354--COST REIMBURSEMENT
(DEC 1991)
(a) This clause provides for indemnification under 10 U.S.C. 2354 if the Contractor meets all the terms and conditions of this clause.
(b) Claims, losses, and damages covered—
(1) Claims by third persons for death, bodily injury, sickness, or disease, or the loss, damage, or lost use of property. Claims include those for reasonable expenses of litigation or settlement. The term “third persons” includes employees of the Contractor;
(2) The loss, damage, and lost use of the Contractor's property, but excluding lost profit; and
(3) Loss, damage, or lost use of the Government's property.
(c) The claim, loss, or damage—
(1) Must arise from the direct performance of this contract;
(2) Must not be compensated by insurance or other means, or be within deductible amounts of the Contractor's insurance;
(3) Must result from an unusually hazardous risk as specifically defined in the contract;
(4) Must not result from willful misconduct or lack of good faith on the part of any of the Contractor's directors or officers, managers, superintendents, or other equivalent representatives who have supervision or direction of—
(i) All or substantially all of the Contractor's business;
(ii) All or substantially all of the Contractor's operations at any one plant or separate location where this contract is being performed; or
(iii) A separate and complete major industrial operation connected with the performance of this contract;
(5) Must not be a liability assumed under any contract or agreement (except for subcontracts covered by paragraph (i) of this clause), unless the Contracting Officer (or in contracts with the Department of the Navy, the Department) specifically approved the assumption of liability; and
(6) Must be certified as just and reasonable by the Secretary of the department or designated representative.
(d) A reduction of the insurance coverage maintained by the Contractor on the date of the execution of this contract shall not increase the Government's liability under this clause unless the Contracting Officer consents, and the contract price is equitably adjusted, if appropriate, to reflect the Contractor's consideration for the Government's assumption of increased liability.
(e) Notice. The Insurance--Liability to Third Persons clause of this contract applies also to claims under this clause. In addition, the Contractor shall—
(1) Promptly notify the Contracting Officer of any occurrence, action, or claim that might trigger the Government's liability under this clause;
(2) Furnish the proof or evidence of any claim, loss, or damage in the form and manner that the Government requires; and
(3) Immediately provide copies of all pertinent papers that the contractor receives or has received.
(f) The Government may direct, participate in, and supervise the settlement or defense of the claim or action. The Contractor shall comply with the Government's directions, and execute any authorizations required.
(g) The Limitation of Cost clause of this contract does not apply to the Government's obligations under this clause. The obligations under this clause are excepted from the release required by the Allowable Cost, Fee, and Payment clause of this contract.
(h) Under this clause, a claim, loss, or damage arises from the direct performance of this contract if the cause of the claim, loss, or damage occurred during the period of performance of this contract or as a result of the performance of this contract.
(i) Flowdown. The Government shall indemnify the Contractor if the Contractor has an obligation to indemnify a subcontractor under any subcontract at any tier under this contract for the unusually hazardous risk identified in this contract only if—
(1) The Contracting Officer gave prior written approval for the Contractor to provide in a subcontract for the Contractor to indemnify the subcontractor for unusually hazardous risks defined in this contract;
(2) The Contracting Officer approved those indemnification provisions;
(3) The subcontract indemnification provisions entitle the Contractor, or the Government, or both, to direct, participate in, and supervise the settlement or defense of relevant actions and claims; and
(4) The subcontract provides the same rights and duties, the same provisions for notice, furnishing of paper and the like, between the Contractor and the subcontractor, as exist between the Government and the Contractor under this clause.
(j) The Government may discharge its obligations under paragraph (i) of this clause by making payments directly to subcontractors or to persons to whom the subcontractors may be liable.
(k) The rights and obligations of the parties under this clause shall survive the termination, expiration, or completion of this contract.
(End of clause)
As prescribed in 235.072(a), use the following clause:
ANIMAL WELFARE (DEC 2014)
(a)(1) The Contractor shall register its research, development, test, and evaluation or training facility with the Secretary of Agriculture in accordance with 7 U.S.C. 2136 and 9 CFR subpart C, and section 2.30, unless otherwise exempt from this requirement by meeting the conditions in 7 U.S.C. 2136 and 9 CFR parts 1 through 4 for the duration of the activity. The Contractor shall have its proposed animal use approved in accordance with Department of Defense Instruction (DoDI) 3216.01, Use of Animals in DoD Programs, by a DoD Component Headquarters Oversight Office. The Contractor shall furnish evidence of such registration and approval to the Contracting Officer before beginning work under this contract.
(2) The Contractor shall make its animals, and all premises, facilities, vehicles, equipment, and records that support animal care available during business hours and at other times mutually agreeable to the Contractor and the United States Department of Agriculture Office of Animal and Plant Health Inspection Service (USDA/APHIS) representative, personnel representing the DoD component oversight offices, as well as the Contracting Officer, to ascertain that the Contractor is compliant with 7 U.S.C. 2131-2159 and 9 CFR parts 1 through 4.
(b) The Contractor shall acquire animals in accordance with DoDI 3216.01, current at time of award (http://www.dtic.mil/whs/directives/corres/pdf/321601p.pdf).
(c) The Contractor agrees that the care and use of animals will conform with the pertinent laws of the United States, regulations of the Department of Agriculture, and policies and procedures of the Department of Defense (see 7 U.S.C. 2131 et seq., and 9 CFR subchapter A, parts 1 through 4, DoDI 3216.01, Army Regulation 40-33/ SECNAVINST 3900.38C/AFMAN 40-401(I)/DARPAINST 18/USUHSINST 3203). The Contractor shall also comply with DoDI 1322.24, Medical Readiness Training, if this contract includes acquisition of training.
(d) The Contracting Officer may immediately suspend, in whole or in part, work and further payments under this contract for failure to comply with the requirements of paragraphs (a) through (c) of this clause.
(1) The suspension will stay in effect until the Contractor complies with the requirements.
(2) Failure to complete corrective action within the time specified by the Contracting Officer may result in termination of this contract and, if applicable, removal of the Contractor's name from the approved vendor list for live animals used in medical training.
(e) The Contractor may request registration of its facility by contacting USDA/APHIS/AC, 4700 River Road, Unit 84, Riverdale, MD 20737-1234, or via the APHIS Animal Care website at: http://www.aphis.usda.gov/wps/portal/aphis/ourfocus/animalwelfare.
(f) The Contractor shall include the substance of this clause, including this paragraph (f), in all subcontracts involving research, development, test, and evaluation or training that use live vertebrate animals.
(End of clause)
252.235-7003 Frequency Authorization.
Basic. As prescribed in 235.072(b) and (b)(1), use the following clause:
FREQUENCY AUTHORIZATION—BASIC (MAR 2014)
(a) The Contractor shall obtain authorization for radio frequencies required in support of this contract.
(b) For any experimental, developmental, or operational equipment for which the appropriate frequency allocation has not been made, the Contractor shall provide the technical operating characteristics of the proposed electromagnetic radiating device to the Contracting Officer during the initial planning, experimental, or developmental phase of contract performance.
(c) The Contracting Officer shall furnish the procedures for obtaining radio frequency authorization.
(d) The Contractor shall include this clause, including this paragraph (d), in all subcontracts requiring the development, production, construction, testing, or operation of a device for which a radio frequency authorization is required.
(End of clause)
Alternate I. As prescribed in 235.072(b) and (b)(2), use the following clause, which uses a different paragraph (c) than the basic clause:
FREQUENCY AUTHORIZATION—ALTERNATE I (MAR 2014)
(a) The Contractor shall obtain authorization for radio frequencies required in support of this contract.
(b) For any experimental, developmental, or operational equipment for which the appropriate frequency allocation has not been made, the Contractor shall provide the technical operating characteristics of the proposed electromagnetic radiating device to the Contracting Officer during the initial planning, experimental, or developmental phase of contract performance.
(c) The contractor shall use DD Form 1494, Application for Equipment Frequency Allocation, to obtain radio frequency authorization.
(d) The Contractor shall include this clause, including this paragraph (d), in all subcontracts requiring the development, production, construction, testing, or operation of a device for which a radio frequency authorization is required.
(End of clause)
252.235-7004 Protection of Human Subjects.
As prescribed in 235.072(e), use the following clause:
PROTECTION OF HUMAN SUBJECTS (JUL 2009)
(a) Definitions. As used in this clause—
(1) “Assurance of compliance” means a written assurance that an institution will comply with requirements of 32 CFR Part 219, as well as the terms of the assurance, which the Human Research Protection Official determines to be appropriate for the research supported by the Department of Defense (DoD) component (32 CFR 219.103).
(2) “Human Research Protection Official (HRPO)” means the individual designated by the head of the applicable DoD component and identified in the component’s Human Research Protection Management Plan as the official who is responsible for the oversight and execution of the requirements of this clause, although some DoD components may use a different title for this position.
(3) “Human subject” means a living individual about whom an investigator (whether professional or student) conducting research obtains data through intervention or interaction with the individual, or identifiable private information (32 CFR 219.102(f)). For example, this could include the use of human organs, tissue, and body fluids from individually identifiable living human subjects as well as graphic, written, or recorded information derived from individually identifiable living human subjects.
(4) “Institution” means any public or private entity or agency (32 CFR 219.102(b)).
(5) “Institutional Review Board (IRB)” means a board established for the purposes expressed in 32 CFR Part 219 (32 CFR 219.102(g)).
(6) “IRB approval” means the determination of the IRB that the research has been reviewed and may be conducted at an institution within the constraints set forth by the IRB and by other institutional and Federal requirements (32 CFR 219.102(h)).
(7) “Research” means a systematic investigation, including research, development, testing, and evaluation, designed to develop or contribute to generalizable knowledge. Activities that meet this definition constitute research for purposes of 32 CFR Part 219, whether or not they are conducted or supported under a program that is considered research for other purposes. For example, some demonstration and service programs may include research activities (32 CFR 219.102(d)).
(b) The Contractor shall oversee the execution of the research to ensure compliance with this clause. The Contractor shall comply fully with 32 CFR Part 219 and DoD Directive 3216.02, applicable DoD component policies, 10 U.S.C. 980, and, when applicable, Food and Drug Administration policies and regulations.
(c) The Contractor shall not commence performance of research involving human subjects that is covered under 32 CFR Part 219 or that meets exemption criteria under 32 CFR 219.101(b), or expend funding on such effort, until and unless the conditions of either the following paragraph (c)(1) or (c)(2) have been met:
(1) The Contractor furnishes to the HRPO, with a copy to the Contracting Officer, an assurance of compliance and IRB approval and receives notification from the Contracting Officer that the HRPO has approved the assurance as appropriate for the research under the Statement of Work and also that the HRPO has reviewed the protocol and accepted the IRB approval for compliance with the DoD component policies. The Contractor may furnish evidence of an existing assurance of compliance for acceptance by the HRPO, if an appropriate assurance has been approved in connection with previous research. The Contractor shall notify the Contracting Officer immediately of any suspensions or terminations of the assurance.
(2) The Contractor furnishes to the HRPO, with a copy to the Contracting Officer, a determination that the human research proposed meets exemption criteria in 32 CFR 219.101(b) and receives written notification from the Contracting Officer that the exemption is determined acceptable. The determination shall include citation of the exemption category under 32 CFR 219.101(b) and a rationale statement. In the event of a disagreement regarding the Contractor’s furnished exemption determination, the HRPO retains final judgment on what research activities or classes of research are covered or are exempt under the contract.
(d) DoD staff, consultants, and advisory groups may independently review and inspect the Contractor’s research and research procedures involving human subjects and, based on such findings, DoD may prohibit research that presents unacceptable hazards or otherwise fails to comply with DoD procedures.
(e) Failure of the Contractor to comply with the requirements of this clause will result in the issuance of a stop-work order under Federal Acquisition Regulation clause 52.242-15 to immediately suspend, in whole or in part, work and further payment under this contract, or will result in other issuance of suspension of work and further payment for as long as determined necessary at the discretion of the Contracting Officer.
(f) The Contractor shall include the substance of this clause, including this paragraph (f), in all subcontracts that may include research involving human subjects in accordance with 32 CFR Part 219, DoD Directive 3216.02, and 10 U.S.C. 980, including research that meets exemption criteria under 32 CFR 219.101(b). This clause does not apply to subcontracts that involve only the use of cadaver materials.
(End of clause)
252.235-7010 Acknowledgment of Support and Disclaimer.
As prescribed in 235.072(c), use the following clause:
ACKNOWLEDGMENT OF SUPPORT AND DISCLAIMER (MAY 1995)
(a) The Contractor shall include an acknowledgment of the Government’s support in the publication of any material based on or developed under this contract, stated in the following terms: This material is based upon work supported by the (name of contracting agency(ies)) under Contract No. (Contracting agency(ies) contract number(s)).
(b) All material, except scientific articles or papers published in scientific journals, must, in addition to any notices or disclaimers by the Contractor, also contain the following disclaimer: Any opinions, findings and conclusions or recommendations expressed in this material are those of the author(s) and do not necessarily reflect the views of the (name of contracting agency(ies)).
(End of clause)
252.235-7011 Final Scientific or Technical Report.
As prescribed in 235.072(d), use the following clause:
FINAL SCIENTIFIC OR TECHNICAL REPORT (JAN 2015)
The Contractor shall—
(a) Submit an electronic copy of the approved final scientific or technical report, not a summary, delivered under this contract to the Defense Technical Information Center (DTIC)] through the web-based input system at http://www.dtic.mil/dtic/submit/ as required by DoD Instruction 3200.12, DoD Scientific and Technical Information Program (STIP). Include a completed Standard Form (SF) 298, Report Documentation Page, in the document, or complete the web-based SF 298.
(b) For instructions on submitting multi-media reports, follow the instructions at http://www.dtic.mil/dtic/submit.
(c) Email classified reports (up to Secret) to TR@DTIC.SMIL.MIL. If a SIPRNET email capability is not available, follow the classified submission instructions at http://www.dtic.mil/dtic/submit/.
(End of clause)
252.236-7000 Modification Proposals--Price Breakdown.
As prescribed in 236.570(a), use the following clause:
MODIFICATION PROPOSALS--PRICE BREAKDOWN (DEC 1991)
(a) The Contractor shall furnish a price breakdown, itemized as required and within the time specified by the Contracting Officer, with any proposal for a contract modification.
(b) The price breakdown—
(1) Must include sufficient detail to permit an analysis of profit, and of all costs for—
(i) Material;
(ii) Labor;
(iii) Equipment;
(iv) Subcontracts; and
(v) Overhead; and
(2) Must cover all work involved in the modification, whether the work was deleted, added, or changed.
(c) The Contractor shall provide similar price breakdowns to support any amounts claimed for subcontracts.
(d) The Contractor's proposal shall include a justification for any time extension proposed.
(End of clause)
252.236-7001 Contract Drawings and Specifications.
As prescribed in 236.570(a), use the following clause:
CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall—
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title |
File |
Drawing No. |
(End of clause)
252.236-7002 Obstruction of Navigable Waterways.
As prescribed in 236.570(b)(1), use the following clause:
OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991)
(a) The Contractor shall—
(1) Promptly recover and remove any material, plant, machinery, or appliance which the contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;
(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer; and
(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.
(b) The Contracting Officer may—
(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and
(2) Deduct the cost of removal from any monies due or to become due to the Contractor; or
(3) Recover the cost of removal under the Contractor's bond.
(c) The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et.seq.).
(End of clause)
252.236-7003 Payment for Mobilization and Preparatory Work.
As prescribed in 236.570(b)(2), use the following clause:
PAYMENT FOR MOBILIZATION AND PREPARATORY WORK (JAN 1997)
(a) The Government will make payment to the Contractor under the procedures in this clause for mobilization and preparatory work under item no. ____________________.
(b) Payments will be made for actual payments by the Contractor on work preparatory to commencing actual work on the construction items for which payment is provided under the terms of this contract, as follows—
(1) For construction plant and equipment exceeding $25,000 in value per unit (as appraised by the Contracting Officer at the work site) acquired for the execution of the work;
(2) Transportation of all plant and equipment to the site;
(3) Material purchased for the prosecution of the contract, but not to be incorporated in the work;
(4) Construction of access roads or railroads, camps, trailer courts, mess halls, dormitories or living quarters, field headquarters facilities, and construction yards;
(5) Personal services; and
(6) Hire of plant.
(c) Requests for payment must include—
(1) An account of the Contractor's actual expenditures;
(2) Supporting documentation, including receipted bills or copies of payrolls and freight bills; and
(3) The Contractor's documentation—
(i) Showing that it has acquired the construction plant, equipment, and material free from all encumbrances;
(ii) Agreeing that the construction plant, equipment, and material will not be removed from the site without the written permission of the Contracting Officer; and
(iii) Agreeing that structures and facilities prepared or erected for the prosecution of the contract work will be maintained and not dismantled prior to the completion and acceptance of the entire work, without the written permission of the Contracting Officer.
(d) Upon receiving a request for payment, the Government will make payment, less any prescribed retained percentage, if—
(1) The Contracting Officer finds the—
(i) Construction plant, material, equipment, and the mobilization and preparatory work performed are suitable and necessary to the efficient prosecution of the contract; and
(ii) Preparatory work has been done with proper economy and efficiency.
(2) Payments for construction plant, equipment, material, and structures and facilities prepared or erected for prosecution of the contract work do not exceed—
(i) The Contractor's cost for the work performed less the estimated value upon completion of the contract; and
(ii) 100 percent of the cost to the contractor of any items having no appreciable salvage value; and
(iii) 75 percent of the cost to the contractor of items which do have an appreciable salvage value.
(e)(1) Payments will continue to be made for item no. _____________, and all payments will be deducted from the contract price for this item, until the total deductions reduce this item to zero, after which no further payments will be made under this item.
(2) If the total of payments so made does not reduce this item to zero, the balance will be paid to the Contractor in the final payment under the contract.
(3) The retained percentage will be paid in accordance with the Payments to Contractor clause of this contract.
(f) The Contracting Officer shall determine the value and suitability of the construction plant, equipment, materials, structures and facilities. The Contracting Officer's determinations are not subject to appeal.
(End of clause)
252.236-7004 Payment for Mobilization and Demobilization.
As prescribed in 236.570(b)(2), use the following clause:
PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (DEC 1991)
(a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item.
(1) ______ percent of the lump sum price upon completion of the contractor's mobilization at the work site.
(2) The remaining ______ percent upon completion of demobilization.
(b) The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract.
(1) Failure to justify such price to the satisfaction of the Contracting Officer will result in payment, as determined by the Contracting Officer, of—
(i) Actual mobilization costs at completion of mobilization;
(ii) Actual demobilization costs at completion of demobilization; and
(iii) The remainder of this item in the final payment under this contract.
(2) The Contracting Officer's determination of the actual costs in paragraph (b)(1)of this clause is not subject to appeal.
(End of clause)
252.236-7005 Airfield Safety Precautions.
As prescribed in 236.570(b)(3), use the following clause. At some airfields, the width of the primary surface is 1,500 feet (750 feet on each side of the runway centerline). In such instances, substitute the proper width in the clause.
AIRFIELD SAFETY PRECAUTIONS (DEC 1991)
(a) Definitions. As used in this clause—
(1) “Landing areas” means—
(i) The primary surfaces, comprising the surface of the runway, runway shoulders, and lateral safety zones. The length of each primary surface is the same as the runway length. The width of each primary surface is 2,000 feet (1,000 feet on each side of the runway centerline);
(ii) The “clear zone” beyond the ends of each runway, i.e., the extension of the primary surface for a distance of 1,000 feet beyond each end of each runway;
(iii) All taxiways, plus the lateral clearance zones along each side for the length of the taxiways (the outer edge of each lateral clearance zone is laterally 250 feet from the far or opposite edge of the taxiway, e.g., a 75-foot-wide taxiway would have a combined width of taxiway and lateral clearance zones of 425 feet); and
(iv) All aircraft parking aprons, plus the area 125 feet in width extending beyond each edge all around the aprons.
(2) “Safety precaution areas” means those portions of approach-departure clearance zones and transitional zones where placement of objects incident to contract performance might result in vertical projections at or above the approach-departure clearance, or the transitional surface.
(i) The “approach-departure clearance surface” is an extension of the primary surface and the clear zone at each end of each runway, for a distance of 50,000 feet, first along an inclined (glide angle) and then along a horizontal plane, both flaring symmetrically about the runway centerline extended.
(A) The inclined plane (glide angle) begins in the clear zone 200 feet past the end of the runway (and primary surface) at the same elevation as the end of the runway. It continues upward at a slope of 50:1 (1 foot vertically for each 50 feet horizontally) to an elevation of 500 feet above the established airfield elevation. At that point the plane becomes horizontal, continuing at that same uniform elevation to a point 50,000 feet longitudinally from the beginning of the inclined plane (glide angle) and ending there.
(B) The width of the surface at the beginning of the inclined plane (glide angle) is the same as the width of the clear zone. It then flares uniformly, reaching the maximum width of 16,000 feet at the end.
(ii) The “approach-departure clearance zone” is the ground area under the approach-departure clearance surface.
(iii) The “transitional surface” is a sideways extension of all primary surfaces, clear zones, and approach-departure clearance surfaces along inclined planes.
(A) The inclined plane in each case begins at the edge of the surface.
(B) The slope of the incline plane is 7:1 (1 foot vertically for each
7 feet horizontally). It continues to the point of intersection with the—
(1) Inner horizontal surface (which is the horizontal plane
150 feet above the established airfield elevation); or
(2) Outer horizontal surface (which is the horizontal plane
500 feet above the established airfield elevation), whichever is applicable.
(iv) The “transitional zone” is the ground area under the transitional surface. (It adjoins the primary surface, clear zone, and approach-departure clearance zone.)
(b) General.
(1) The Contractor shall comply with the requirements of this clause while—
(i) Operating all ground equipment (mobile or stationary);
(ii) Placing all materials; and
(iii) Performing all work, upon and around all airfields.
(2) The requirements of this clause are in addition to any other safety requirements of this contract.
(c) The Contractor shall—
(1) Report to the Contracting Officer before initiating any work;
(2) Notify the Contracting Officer of proposed changes to locations and operations;
(3) Not permit either its equipment or personnel to use any runway for purposes other than aircraft operation without permission of the Contracting Officer, unless the runway is—
(i) Closed by order of the Contracting Officer; and
(ii) Marked as provided in paragraph (d)(2) of this clause;
(4) Keep all paved surfaces, such as runways, taxiways, and hardstands, clean at all times and, specifically, free from small stones which might damage aircraft propellers or jet aircraft;
(5) Operate mobile equipment according to the safety provisions of this clause, while actually performing work on the airfield. At all other times, the Contractor shall remove all mobile equipment to locations—
(i) Approved by the Contracting Officer;
(ii) At a distance of at least 750 feet from the runway centerline, plus any additional distance; and
(iii) Necessary to ensure compliance with the other provisions of this clause; and
(6) Not open a trench unless material is on hand and ready for placing in the trench. As soon as practicable after material has been placed and work approved, the Contractor shall backfill and compact trenches as required by the contract. Meanwhile, all hazardous conditions shall be marked and lighted in accordance with the other provisions of this clause.
(d) Landing areas. The Contractor shall—
(1) Place nothing upon the landing areas without the authorization of the Contracting Officer;
(2) Outline those landing areas hazardous to aircraft, using (unless otherwise authorized by the Contracting Officer) red flags by day, and electric, battery-operated low-intensity red flasher lights by night;
(3) Obtain, at an airfield where flying is controlled, additional permission from the control tower operator every time before entering any landing area, unless the landing area is marked as hazardous in accordance with paragraph (d)(2) of this clause;
(4) Identify all vehicles it operates in landing areas by means of a flag on a staff attached to, and flying above, the vehicle. The flag shall be three feet square, and consist of a checkered pattern of international orange and white squares of 1 foot on each side (except that the flag may vary up to ten percent from each of these dimensions);
(5) Mark all other equipment and materials in the landing areas, using the same marking devices as in paragraph (d)(2) of this clause; and
(6) Perform work so as to leave that portion of the landing area which is available to aircraft free from hazards, holes, piles of material, and projecting shoulders that might damage an airplane tire.
(e) Safety precaution areas. The Contractor shall—
(1) Place nothing upon the safety precaution areas without authorization of the Contracting Officer;
(2) Mark all equipment and materials in safety precaution areas, using (unless otherwise authorized by the Contracting Officer) red flags by day, and electric, battery-operated, low-intensity red flasher lights by night; and
(3) Provide all objects placed in safety precaution areas with a red light or red lantern at night, if the objects project above the approach-departure clearance surface or above the transitional surface.
(End of clause)
As prescribed in 236.570(b)(4), use the following provision:
COST LIMITATION (JAN 1997)
(a) Certain items in this solicitation are subject to statutory cost limitations. The limitations are stated in the Schedule.
(b) An offer which does not state separate prices for the items identified in the Schedule as subject to a cost limitation may be considered nonresponsive.
(c) Prices stated in offers for items subject to cost limitations shall include an appropriate apportionment of all costs, direct and indirect, overhead, and profit.
(d) Offers may be rejected which—
(1) Are materially unbalanced for the purpose of bringing items within cost limitations; or
(2) Exceed the cost limitations, unless the limitations have been waived by the Government prior to award.
(End of provision)
252.236-7007 Additive or Deductive Items.
As prescribed in 236.570(b)(5), use the following provision:
ADDITIVE OR DEDUCTIVE ITEMS (DEC 1991)
(a) The low offeror and the items to be awarded shall be determined as follows—
(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.
(2) The low offeror shall be the Offeror that—
(i) Is otherwise eligible for award; and
(ii) Offers the lowest aggregate amount for the first or base bid item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive items that provide the most features within the funds determined available.
(3) The Contracting Officer shall evaluate all bids on the basis of the same additive or deductive items.
(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and
(ii) Add that next item if an award may be made that includes that item and is within the available funds.
(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if—
(1) It is in the best interest of the Government;
(2) Funds are available at the time of award; and
(3) The low offeror's price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.
(c) Example. The amount available is $100,000. Offeror A's base bid and four additives (in the order stated in the list of priorities in the bid Schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B's base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A's bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.
(End of provision)
252.236-7008 Contract Prices--Bidding Schedules.
As prescribed in 236.570(b)(6), use the following provision:
CONTRACT PRICES--BIDDING SCHEDULES (DEC 1991)
(a) The Government's payment for the items listed in the Bidding Schedule shall constitute full compensation to the Contractor for—
(1) Furnishing all plant, labor, equipment, appliances, and materials; and
(2) Performing all operations required to complete the work in conformity with the drawings and specifications.
(b) The Contractor shall include in the prices for the items listed in the Bidding Schedule all costs for work in the specifications, whether or not specifically listed in the Bidding Schedule.
(End of provision)
252.236-7010 Overseas Military Construction--Preference for United States Firms.
As prescribed in 236.570(c)(1), use the following provision:
OVERSEAS MILITARY CONSTRUCTION--PREFERENCE FOR
UNITED STATES FIRMS (JAN 1997)
(a) Definition. “United States firm,” as used in this provision, means a firm incorporated in the United States that complies with the following:
(1) The corporate headquarters are in the United States;
(2) The firm has filed corporate and employment tax returns in the United States for a minimum of 2 years (if required), has filed State and Federal income tax returns (if required) for 2 years, and has paid any taxes due as a result of these filings; and
(3) The firm employs United States citizens in key management positions.
(b) Evaluation. Offers from firms that do not qualify as United States firms will be evaluated by adding 20 percent to the offer.
(c) Status. The offeror ______ is, ______ is not a United States firm.
(End of provision)
252.236-7011 Overseas Architect-Engineer Services--Restriction to United States Firms.
As prescribed in 236.609-70, use the following provision:
OVERSEAS ARCHITECT-ENGINEER SERVICES--RESTRICTION TO
UNITED STATES FIRMS (JAN 1997)
(a) Definition. “United States firm,” as used in this provision, means a firm incorporated in the United States that complies with the following:
(1) The corporate headquarters are in the United States;
(2) The firm has filed corporate and employment tax returns in the United States for a minimum of 2 years (if required), has filed State and Federal income tax returns (if required) for 2 years, and has paid any taxes due as a result of these filings; and
(3) The firm employs United States citizens in key management positions.
(b) Restriction. Military construction appropriations acts restrict award of a contract, resulting from this solicitation, to a United States firm or a joint venture of United States and host nation firms.
(c) Status. The offeror confirms, by submission of its offer, that it is a United States firm or a joint venture of United States and host nation firms.
(End of provision)
252.236-7012 Military Construction on Kwajalein Atoll--Evaluation Preference.
As prescribed in 236.570(c)(2), use the following provision:
MILITARY CONSTRUCTION ON KWAJALEIN ATOLL--EVALUATION PREFERENCE (MAR 1998)
(a) Definitions. As used in this provision
(1) “Marshallese firm” means a local firm incorporated in the Marshall Islands, or otherwise legally organized under the laws of the Marshall Islands, that
(i) Is more than 50 percent owned by citizens of the Marshall Islands; or
(ii) Complies with the following:
(A) The firm has done business in the Marshall Islands on a continuing basis for not less than 3 years prior to the date of issuance of this solicitation;
(B) Substantially all of the firm’s directors of local operations, senior staff, and operating personnel are resident in the Marshall Islands or are U.S. citizens; and
(C) Most of the operating equipment and physical plant are in the Marshall Islands.
(2) “United States firm” means a firm incorporated in the United States that complies with the following:
(i) The corporate headquarters are in the United States;
(ii) The firm has filed corporate and employment tax returns in the United States for a minimum of 2 years (if required), has filed State and Federal income tax returns (if required) for 2 years, and has paid any taxes due as a result of these filings; and
(iii) The firm employs United States citizens in key management positions.
(b) Evaluation. Offers from firms that do not qualify as United States firms or Marshallese firms will be evaluated by adding 20 percent to the offer, unless application of the factor would not result in award to a United States firm.
(c) Status. The offeror is ______ a United States firm; ______ a Marshallese firm; _______ Other.
(End of provision)
252.236-7013 Requirement for Competition Opportunity for American Steel Producers, Fabricators, and Manufacturers.
As prescribed in 236.570(d), use the following clause:
REQUIREMENT FOR COMPETITION OPPORTUNITY FOR AMERICAN STEEL
PRODUCERS, FABRICATORS, AND MANUFACTURERS (JUN 2013)
(a) Definition. “Construction material,” as used in this clause, means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work.
(b) The Contractor shall provide American steel producers, fabricators, and manufacturers the opportunity to compete when acquiring steel as a construction material (e.g., steel beams, rods, cables, plates).
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in any subcontract that involves the acquisition of steel as a construction material, including subcontracts for the acquisition of commercial items.
(End of clause)