NMCARS PART 5243 CONTRACT MODIFICATIONS



PART 5243 CONTRACT MODIFICATIONS

SUBPART 5243.1—GENERAL

5243.102 Policy.

5243.102-90 Use of modifications for additional quantities.

DoN policy is to avoid the use of contract modifications for additional quantities as a means of purchasing new requirements of supplies, when such a procedure would result in prolonging the life of the contract beyond the time when final settlement would normally be made.

SUBPART 5243.2—CHANGE ORDERS

5243.201 General.

(90) Each undefinitized change order shall include a not-to-exceed price unless the CCO waives this requirement.

(91) The policies and procedures of DFARS 217.74 should be applied to change orders (except value engineering change proposals (VECP's)) to the maximum extent practicable.

(92) The use of VECP's is encouraged due to the potential savings and system improvements that may be realized.

(a) Prompt action should be taken to implement those VECP's deemed to be technically sound.

(b) When considering VECP's, contracting officers should consider the impact on the projected savings that the normal negotiation and definitization process would have versus use of an unpriced change order. Unpriced contract modifications that implement VECP's should:

(1) Define minimum unit cost savings, and

(2) Define maximum development/implementation costs