Subpart 5232.6 - CONTRACT DEBTS
5232.607 Installment payments and deferment of collection.
5232.607-2 Deferment of collection.
(c)(2) Information should be submitted with all requests, whether or not an appeal is pending, or a Dispute action filed. In addition, include the following information:
(a) If applicable, the final decision, the appeal, the status of the appeal, and the name of the DON lead trial attorney.
(b) The appropriation account(s) that will be credited with the repayment or debited with the liability if the appeal is successful.
(c) Points of contact at the cognizant paying and contract administration offices.
(d) Any small business concern representation.
5232.690 DON claims against a contractor.
The review and approval requirements of 5233.9001 apply to the settlement of DON claims against contractors.