49.207 Limitation on settlements.

The total amount payable to the contractor for a settlement, before deducting disposal or other credits and exclusive of settlement costs, must not exceed the contract price less payments otherwise made or to be made under the contract.

Parent topic: Subpart 49.2 - Additional Principles for Fixed-Price Contracts Terminated for Convenience